Influence Of Prefabrication Technology On Cost & Time Dealing With Microsoft Project

Mukunda B. Shep Prof. Ashish P. Waghmare

Subject area: Science,Engineering and Technology  ·  Area of research: Civil Engineering

Abstract

This paper proposes a model for quantitatively evaluating the possible impacts arising from the application of prefabrication technology on construction. The object of this paper is to identify new technologies or methodologies in the Construction Industry that could require new training or up-skilling of the trades and semi-skilled workforce. Prefabrication has been widely regarded as a sustainable construction method in terms of its impact on environmental protection. The main focus is on to reduce the cost & time of whole project by using PEB with Microsoft Project.

Keywords

Time, Cost, MSP, Prefabricated Technology, Feasibility

References

[1] Impact Of Prefabricated Technology & Equipment On The Profitability Using Primavera T.Subramani1, M. Muhammed Ansar2

[2] Studies of the Prefabricated Housing Construction Market in Poland By Elzbieta Radziszewska -Zielina, Monika Glen.

[3] A Study of Cost Comparison of Precast Concrete Vs Cast-In-Place Concrete VaishaliTurai1 & Ashish Waghmare2

[4] Mohamed Nor Azhari Azman’ The Perspective View Of Malaysian Industrialized Building System (Ibs) Under Ibs Precast Manufacturing

[5] Omid Reza BAGHCHESARAEI’ Behavior of Prefabricated Structures in Developed and Developing Countries’

[6] Gerhard Girmscheid, Industrialization in Building Construction – Production Technology or Management Concept

[7] Yuan, HP’ Investigating waste reduction potential in the upstream processes of offshore prefabrication construction’

[8] Hamza Khan’ Study on the Trends & Usage of Prefabrication and Modularization: Increasing Productivity in the Construction Industry’ ISSN 2278-3652 Volume 8, Number 2 (2017)

[9] Tianying Li’ Strategies for Implementation of Integrated Prefabrication Technology in Small Scale Isolated Buildings’

[10] Hong Xue’ Factors Affecting the Capital Cost of Prefabrication—A Case Study of China’ Published: 24 August 2017

How to cite this paper

Mukunda B. Shep, Prof. Ashish P. Waghmare "Influence Of Prefabrication Technology On Cost & Time Dealing With Microsoft Project" Iconic Research And Engineering Journals Volume 2 Issue 9 2019 Page 169-174
Mukunda B. Shep, Prof. Ashish P. Waghmare "Influence Of Prefabrication Technology On Cost & Time Dealing With Microsoft Project" Iconic Research And Engineering Journals, vol. 2, no. 9, Mar. 2019
Mukunda B. Shep, Prof. Ashish P. Waghmare (2019). Influence Of Prefabrication Technology On Cost & Time Dealing With Microsoft Project. Iconic Research And Engineering Journals, 2(9).
Mukunda B. Shep, Prof. Ashish P. Waghmare "Influence Of Prefabrication Technology On Cost & Time Dealing With Microsoft Project" Iconic Research And Engineering Journals, vol. 2, no. 9, Mar. 2019.
@article{1701024,
      author = {Mukunda B. Shep, Prof. Ashish P. Waghmare},
      title = {Influence Of Prefabrication Technology On Cost & Time Dealing With Microsoft Project},
      journal = {Iconic Research And Engineering Journals},
      year = {2019},
      volume = {2},
      number = {9},
      pages = {169-174},
      issn = {2456-8880},
      url = {https://www.irejournals.com/formatedpaper/1701024.pdf},
      abstract = {This paper proposes a model for quantitatively evaluating the possible impacts arising from the application of prefabrication technology on construction. The object of this paper is to identify new technologies or methodologies in the Construction Industry that could require new training or up-skilling of the trades and semi-skilled workforce.  Prefabrication has been widely regarded as a sustainable construction method in terms of its impact on environmental protection. The main focus is on to reduce the cost & time of whole project by using PEB with Microsoft Project.},
      keywords = {Time, Cost, MSP, Prefabricated Technology, Feasibility},