Home / Current Issue / Paper 1701733
Time Delay And Cost Overrun In Construction Projects
Subject area: Science,Engineering and Technology · Area of research: Nagercoil
Abstract
The impact of cost and time overruns on construction projects is an undesirable experience both to the clients and stakeholders in the industry. This has regularly led to dispute, unfriendly working relationship, abandonment, low quality and environmental nuisances. This paper evaluated factors contributing to overruns of highway projects and their impact on projects performance at Tamil Nadu in India .Data were collected through questionnaire administration on professionals in the industry. Frequency index were employed to analyse data collected. Increase in material cost, inaccurate materials estimation and underestimating of project costs among others are the most significant cost factors while the most significant time factors include unexpected site condition, increase in project scope, lack of timely progress payment and inadequate planning.
Keywords
Information, Performance, Cost and Time and Developing Economy.
References
[1] Harris, E.C. (2011), “Construction Sector Poised for Further Growth as Indian Economy Forges Ahead”, viewed 2 April2013.
[2] Henry Alinaitwe, Ruth Apolot and Dan Tindiwensi (2013),” Investigation into the Causes of Delays and Cost Overruns in Uganda’s Public Sector Construction Projects”, Journal of Construction in Developing Countries, Vol.18 (2), No.33-47.
[3] Ibrahim Mahamid1, Amund Bruland (2011),” Cost Overrun Causes in Road Construction Projects: Consultants’ Perspective”, International Conference on Construction and Project Management, Vol.15.
[4] ICRA (2011), “Indian Construction Sector: Opportunities Expand but Execution Remains a Concern” ICRA, India, viewed 2 April2013,
[5] Indo-Italian Chamber of Commerce (2008), “Overview of the Construction Industry in India”, viewed 2April2013,
[6] Jamal M. Assbeihat (2016),”Factors Affecting Delays on Private Construction Projects”, International Journal of Civil Engineering and Technology, Vol.7, Issue 2, No.22-33.
[7] Jergeas, George F. & Ruwanpura, Janaka. (2010), “Why Cost and Schedule Overruns on Mega Oil Sands Projects?” Practice Periodical on Structural Design and Construction, Vol. No. 1,40-43.
[8] Kasimu, M. A. (2012), “Significant Factors that Causes Cost Overruns in Building Construction Project in Nigeria”, Interdisciplinary Journal of Contemporary Research in Business, Vol. 3, No. 11,775-700.
[9] Lee, Jin-Kyung. (2008), “Cost Overrun and Cause in Korean Social Overhead Capital Projects: Roads, Rails, Airports, and Ports”, Journal of Urban Planning and Development, Vol. 134, No. 2,59-62.
[10] Leena Mali, Abhijit Warudkar (2016),” Analysis on Causes of Delay in Construction Industry in Pune City”, International Journal of Innovative Research in Science, Engineering and Technology, Vol.5, Issue 8.
[11] Le-Hoai, Long., Lee, Young Dai. & Lee, Jun Yong. (2008), “Delay and Cost Overruns in Vietnam Large Construction Projects: A Comparison with Other Selected Countries”, Journal of Civil Engineering, Vol. 12, No.6,367- 377.
[12] Lekan Amusan, Dosunmu Dolapo and Opeyemi Joshua (2017), “Cost and Time Performance Information of Building projects in Developing Economy”, International journal of Mechanical Engineering and Technology, Vol.8, No.918-927.
[13] Memon, Aftab Hameed., Rahman, Ismail Abdul., Abdullah, Mohd Razaki. &Azis, Ade Asmi Abdu. (2010), “Factors Affecting Construction Cost in Mara Large Construction Project: Perspective of Project Management Consultant”, International Journal of Sustainable Construction Engineering & Technology, Vol. 1, No. 2, 41-54.
[14] Memon, Aftab Hameed., Rahman, Ismail Abdul. & Azis, Ade Asmi Abdu. (2011), “Preliminary Study on Causative Factors Leading to Construction Cost Overrun”, Journal of Sustainable Construction Engineering & Technology, Vol. 2, Issue. 1,57-71.
[15] Mohammad Almohammad, Omar Bin Jamaludin. (2018), “ A Review of Major Causes of Delay in Road Construction Projects”, International Journal of Advanced Engineering and Research Engineering, Vol.5, Issue 9.
[16] Muhamid, Ibrahim. & Bruland, Amund. (2011), “Cost Overrun Causes in Road Construction Projects: Consultants‟ Perspective‟‟, 2nd International Conference on Construction and ProjectManagement.
[17] Murray, Susan L., Grantham, Katie, & Damle, Siddharth B.(2011), “Development of a Generic Risk Matrix to Manage Project Risks”, Journal of Industrial and Systems Engineering, Vol. 5, No. 1,35-51.
[18] Nabil AL-Hazim, Zaydoun Abu Salem (2015),”Delay and Cost Overrun in Road Construction Projects in Jordan”, International Journal of Engineering and Technology, Vol.4, Issue 2.
[19] Naser S. Almutairi (2016),” Causes of Delays on Construction Projects in Kuwait according to opinion of engineers working in Kuwait”,International Journal of Engineering Research and Application, Vol.6, Issue 12, No. 84-96.
[20] Obodoh D. A, Chikasi Obodoh ,” Causes and Effect of Construction Project Delays in Nigerian Construction Industry”, International Journal of Innovative Science Engineering and Technology, Vol.3, Issue 5.
[21] Raj Kapur Shah (2016),” An Exploration of Causes and Cost Overruns in Construction Projects: Case Study of Australia, Malaysia and Ghana”, Journal of College of Engineering and Management, Vol.2, 2016.
[22] Rizwan U. Farooqui, Etikaf Hussain, Muhammad Umer, Sarosh H. Lodi (2012),”Factors Affecting Construction Cost in the Pakistani Construction Industry”,Third International Conference on Construction in Developing Countries.
[23] Mr. Salim S. Mulla, Prof. Ashish P. Waghmare (2015),”A Study of Factors Caused for Time and Cost Overruns in Construction Projects and their Remedial Measures”, International Journal of Engineering Research and Application, Vol.5, Issue.1, No.48-53.
[24] Subhav Singh, Anju Bala, Saurav Dixit, Deekshant Varshney(2018),”Critical Analysis of Causes of Delay in Residential Construction Projects in India”, International Journal of Civil Engineering and Technology, Vol.9, Issue.1, No.330-345.
[25] Sunil Kagel, Meghendra R Mane, Arjun M Chougule (2018),”Time Delay and Cost Overrun in Construction Industry in India”, International Journal of Innovative Research in Science, Engineering and Technology, Vol.7, Issue 12.
[26] Tahir Nawaz, Amjad Ali Ikram,”Causes of schedule overrun in Pakistani construction industry” ,Journals of Mechanical and Civil Engineering, Vol. 5, Issue 4(2013).
[27] Vaibhav Y. Katre, D.M.Ghaitidak, (2016)”Elements of Cost and Schedule Overrun in Construction Projects”, International Journal of Engineering Research and Development, Vol.12, Issue 7, No.64-68.
[28] Veera Vijay. Divi, Sundara Kumar. P (2017),” Analysing Delay Factors in Indian Affecting Construction Projects”, International Journal of Civil Engineering and Technology, Vol.8, Issue 4, No.1938-1953.
How to cite this paper
@article{1701733,
author = {P. Asmitha},
title = {Time Delay And Cost Overrun In Construction Projects},
journal = {Iconic Research And Engineering Journals},
year = {2019},
volume = {3},
number = {5},
pages = {44-51},
issn = {2456-8880},
url = {https://www.irejournals.com/formatedpaper/1701733.pdf},
abstract = {The impact of cost and time overruns on construction projects is an undesirable experience both to the clients and stakeholders in the industry. This has regularly led to dispute, unfriendly working relationship, abandonment, low quality and environmental nuisances. This paper evaluated factors contributing to overruns of highway projects and their impact on projects performance at Tamil Nadu in India .Data were collected through questionnaire administration on professionals in the industry. Frequency index were employed to analyse data collected. Increase in material cost, inaccurate materials estimation and underestimating of project costs among others are the most significant cost factors while the most significant time factors include unexpected site condition, increase in project scope, lack of timely progress payment and inadequate planning.},
keywords = {Information, Performance, Cost and Time and Developing Economy.},
month = {November},
}