Comprehensive Investigation of the Factors That Led to the Abandonment of Lalong's Legacy Projects on the Plateau Between 2015 - 2023

Miri, Timnan Nyantau Godfrey Mangshin Mohorshin Goar, Paul Ishaku

Subject area: Physical Sciences and Environment  ·  Area of research: Environment

DOI: https://doi.org/10.64388/IREV9I4-1711210-6599

Abstract

Project abandonment remains a major challenge to infrastructure development in Nigeria, with significant social, economic, and political consequences. In Plateau State, the administration of Governor Simon BakoLalong initiated the Lalong?s Legacy Projects in 2016, comprising 21facilities - nine primary schools, six secondary schools, and six hospitals - across the 17 Local Government Areas. Although the projects were initially scheduled for completion within 32 weeks at a contract sum of ?59 billion (later revised to ?29 billion in 2021), many remained uncompleted by the end ofthe administration in 2023. This study investigated the causes of project abandonment using survey data from 72 respondents drawn from community members,project staff, government officials, and construction professionals. Data analysis through the Relative Importance Index (RII) revealed that client-related factors, particularly poor contract management (RII = 0.8000) and inappropriate procurement methods (RII = 0.7667), were major contributors. Contractor-related factors such as poor site management (RII = 0.8139) and inadequate technical competence (RII = 0.7917) were also significant. Consultant-related issues, including inadequate design and documentation (RII = 0.8500) and poor feasibility studies (RII = 0.8139), highlighted technical weaknesses. External and community-related influences ranked highest overall, with pandemics and health emergencies (RII = 0.8806), insecurity (RII = 0.8389), and economic instability (RII = 0.7944) exerting the greatest impact. The study concludes that sustainable project delivery requires effective governance, improved technical capacity, and resilience against external disruptions. Recommendations are proposed for government, consultants, and contractors to reduce the risk of project abandonment.

Keywords

Financial Mismanagement, Project Abandonment, Procurement Strategy, Poor Contract Management, Plateau State

How to cite this paper

Miri, Timnan Nyantau, Godfrey Mangshin Mohorshin, Goar, Paul Ishaku "Comprehensive Investigation of the Factors That Led to the Abandonment of Lalong's Legacy Projects on the Plateau Between 2015 - 2023" Iconic Research And Engineering Journals Volume 9 Issue 4 2025 Page 496-506 https://doi.org/10.64388/IREV9I4-1711210-6599
Miri, Timnan Nyantau, Godfrey Mangshin Mohorshin, Goar, Paul Ishaku "Comprehensive Investigation of the Factors That Led to the Abandonment of Lalong's Legacy Projects on the Plateau Between 2015 - 2023" Iconic Research And Engineering Journals, vol. 9, no. 4, Oct. 2025, doi: https://doi.org/10.64388/IREV9I4-1711210-6599
Miri, Timnan Nyantau, Godfrey Mangshin Mohorshin, Goar, Paul Ishaku (2025). Comprehensive Investigation of the Factors That Led to the Abandonment of Lalong's Legacy Projects on the Plateau Between 2015 - 2023. Iconic Research And Engineering Journals, 9(4). doi: https://doi.org/10.64388/IREV9I4-1711210-6599
Miri, Timnan Nyantau, Godfrey Mangshin Mohorshin, Goar, Paul Ishaku "Comprehensive Investigation of the Factors That Led to the Abandonment of Lalong's Legacy Projects on the Plateau Between 2015 - 2023" Iconic Research And Engineering Journals, vol. 9, no. 4, Oct. 2025. Crossref, https://doi.org/10.64388/IREV9I4-1711210-6599
@article{1711210,
      author = {Miri, Timnan Nyantau, Godfrey Mangshin Mohorshin, Goar, Paul Ishaku},
      title = {Comprehensive Investigation of the Factors That Led to the Abandonment of Lalong's Legacy Projects on the Plateau Between 2015 - 2023},
      journal = {Iconic Research And Engineering Journals},
      year = {2025},
      volume = {9},
      number = {4},
      pages = {496-506},
      issn = {2456-8880},
      url = {https://www.irejournals.com/formatedpaper/1711210.pdf},
      abstract = {Project abandonment remains a major challenge to infrastructure development in Nigeria, with significant social, economic, and political consequences. In Plateau State, the administration of Governor Simon BakoLalong initiated the Lalong?s Legacy Projects in 2016, comprising 21facilities - nine primary schools, six secondary schools, and six hospitals - across the 17 Local Government Areas. Although the projects were initially scheduled for completion within 32 weeks at a contract sum of ?59 billion (later revised to ?29 billion in 2021), many remained uncompleted by the end ofthe administration in 2023. This study investigated the causes of project abandonment using survey data from 72 respondents drawn from community members,project staff, government officials, and construction professionals. Data analysis through the Relative Importance Index (RII) revealed that client-related factors, particularly poor contract management (RII = 0.8000) and inappropriate procurement methods (RII = 0.7667), were major contributors. Contractor-related factors such as poor site management (RII = 0.8139) and inadequate technical competence  (RII  =  0.7917)  were  also  significant.  Consultant-related  issues,  including  inadequate  design  and documentation (RII = 0.8500) and poor feasibility studies (RII = 0.8139), highlighted technical weaknesses. External and community-related influences ranked highest overall, with pandemics and health emergencies (RII = 0.8806), insecurity (RII = 0.8389), and economic instability (RII = 0.7944) exerting the greatest impact. The study concludes that sustainable project delivery   requires   effective   governance,   improved   technical   capacity,   and   resilience   against   external   disruptions.  Recommendations are proposed for government, consultants, and contractors to reduce the risk of project abandonment.},
      keywords = {Financial  Mismanagement,  Project  Abandonment,  Procurement  Strategy,  Poor  Contract  Management, Plateau State},
      month = {October},
      doi = {https://doi.org/10.64388/IREV9I4-1711210-6599}
  }