Impact of Risk Factors Associated with Procurement Process On Time Performance of Public Institutional Building Projects in Edo State, Nigeria

Oso, S. B. Amiebenomo, M. I. Dedegu, U. I.

Subject area: Science,Engineering and Technology  ·  Area of research: Construction Procurement and Risk Management

DOI: 10.64388/IREV9I9-1715786

Abstract

Public construction projects in Edo State are frequently challenged by delays, which undermine project objectives, inflate costs and reduce stakeholder satisfaction. The study examines the impact of risk factors associated with procurement process on the time performance of public institutional building projects in Edo State, Nigeria. It identified a generic procurement process; the key risk factors associated with procurement process, the impact of risk factors on time performance, and propose strategies for mitigating risk factors associated with procurement process to improve time performance in selected public institutional building projects. A quantitative survey research design was adopted for the study; primary data were collected through structured questionnaires administered to construction professionals, procurement officers and contractors involved in public institutional projects in Edo State. Quantitative data were analysed using descriptive statistics and regression analysis to establish the strength and significance of relationship between risk factors and time performance. Results indicate that preparation of bidding documents and evaluation criteria were the most important procurement process and the most frequently occurring risks are fraud and corruption. Furthermore, the results reveal that there is a significant high relationship between risk factors associated with procurement process and time performance and comprehensive procurement planning and early risk assessment was identified as the most effective mitigating strategies. The findings underscore the need for streamlined procurement procedures, enhanced capacity building for procurement professionals and the adoption of transparent and efficient contractor prequalification systems. The study concludes that mitigating procurement risk factors is essential to improve the timely delivery of public institutional building projects in Edo State and recommends that there should be policy reforms and the implementation of best practices in public sector procurement to strength project time performance and enhances value for public investment.

Keywords

Procurement Process, Public Institutional Building Projects, Project Delays, Risk Factors, Time performance

References

[1] Oladipo FS, Fatuki AM, Aluko AT (2015) An assessment of major factors affecting construction project cost in Nigeria. Int J Sci Bas Appl Res308-318

[2] Fabi JK, Awolesi JA, Akinseinde OA (2015) An assessment of effect of procurement process on construction project delivery. Proceeding of the Nigerian Institute of Quantity Surveyors, 2nd research conference-NIQS Recon2.

[3] Ogunseye TE, Oladipo O (2025) Procurement delays and project performance in Nigeria public university infrastructural projects. Icon Res Eng J 9 (6): 1886-1909. https://doi.org//10.64388/IREV916-1713068

[4] Suleiman S, Abdullahi A, Isah ML (2025) Budget appropriation risks in procurement of construction projects of public tertiary institutions in Nigeria. J Env Manag Const Res 18 (4): 56-67.

[5] Fariz GWA, Iputu AW (2021) Modelling project characteristics on construction project performance based on time, cost and quality in PT XYZ regional Jabodetabek. The 3rd International Conference on Management of Technology, Innovation and Project, Nov 18, 2021, Easy Chair Preprint.

[6] Effiong EA, Nwoke H, Ugwu KE (2025) Assessment of impact of regulatory guidelines on procurement lead times in World Bank funded projects in Nigeria. J Comm Manag Tour Stud 4 (3): 430-449. Https://doi.org/10.58881/Jcmts.v.3i2.

[7] Public Procurement Act (2007) Public Procurement Reform Program in Nigeria, State House, Abuja, Nigeria.

[8] Edo Public Procurement Law (2020) Edo State Government of Nigeria. Benin City, Nigeria: Edo State

[9] Alhassan D, Aminu MB (2015) Risk factors influencing construction procurement performance in Nigeria. Arid Zon J Eng Tech Env11: 77-88

[10] Fagbemi KB (2025) Impact of risk associated with procurement process on cost performance of public tertiary education institution projects in Ondo State, Nigeria. J Loc Arch Civ Eng 3 (2): 63-68. https://doi.org/10.59810/localengineering.

[11] Stukhart G (1995) Construction Materials Management. New York, USA: Marcel Dekker Inc.

[12] Sukulpat K (2007) Risks in construction project procurement process and the mitigation methods. J Arch/Plan Res Stud 5: 135-145.

[13] Harris F, McCaffer R (2005) Modern Construction Management. 5th Edition. Blackwell Publishing.

[14] Carrillo PM (2005) Lessons learned practices, in Engineering, Procurement and Construction Sector. J Eng Const Arch Manag 12(3): 236-250.

[15] Public Procurement Oversight Authority (2009) The long term policy framework for public procurement in Kenya, Draft Zero.

[16] American Institute of Architects (2011) The Architect’s Handbook of Professional Practice, 13th Edition. Florida: John Wiley and sons, Inc.

[17] Inter-agency Procurement Working Group (2006) UN Procurement Practitioner’s Handbook.

[18] British Standards Institute Group (2011) BS8534 Construction Procurement Policies, Strategies and Procedures-Code of Practice. London: British Standards Institute.

[19] Sanvido V, Konchar M (1997) Comparison of U.S project delivery systems. J Const Eng and Manag 124(6):435-444.

[20] Zhao N, Ying FJ, Tookey J (2022) Construction procurement selection criteria: A review and research agenda. Sust 142215242, 1-16. https://doi.org/10.3390/su142215242

[21] Suleiman S, Ibrahaim S, Adamu AD, Tsado AJ (2024) Management of need assessment risks in procurement of tertiary institution construction projects in Nigeria. J Biod Env Res 4 (4): 62-72.

[22] Odimabo OO, Oduoza CF (2013) Risk Assessment Framework for Building Construction Projects in developing Countries. Int J Cons Eng Manag 2(5): 143-154.

[23] Jahin MA, Naife SA, Saha AK, Mridha MF (2025) AI in supply chain risk assessment: A systematic literature review and bibliometric analaysis. Computer Science, Machine Learning, 1-45.Arxiv:2401.10895, Cornell University.

[24] Khosrozad MM (2026) Risk Assessment. Procurement Quality Assessment Reference

[25] Offiong JB, Ogwueleka AC (2025) Procurement planning improvement strategies and challenges in construction project delivery within the public tertiary education sector. J Cons Proj Manag Innov 15(1):39-52. https://doi.org/10.36615/jcpmi.V.15i1.3745

[26] OECD (2023) Managing risks in the public procurement of goods, services and infrastructure. OECD Public Governance Policy Papers, No. 33

[27] Oguntola, BB (2017) Impact of strategic procurement in realization of organizational goals in a Nigerian private University. Unpublished M.Sc Thesis submitted to Department of Transport and Tourism, College of Management and Social Sciences, Redeemer’s University Ede, Nigeria.

[28] Davidson WD, Wright E (2004) Contract Administration. Leap Text book.

[29] Marcos SL, Bruno D, Flavio L, Fernando B (2022) Fraud, corruption, and collusion in public procurement activities, a systematic literature review on data-driven methods. App Nwork Sci 7 (83): 1-30. https://doi.org/10.1007/s41109-022-00523-6

[30] Jackline AA, Wycliffe A, Wicliffe,O (2024) Influence of tendering process on performance of County Governments in Kenya. Int J Soc Sci Human Res 2 (3): 200-217. https://doi. Org/10.61108/ijsshr.v2i3.136

[31] Hudson WB (2014) Procurement practices affecting effective public projects implantation in Kenya; A case study of Kenya Civil Aviation Authority. Eur J Bus Manag 6(6): 2222-2839.

[32] Dogo PP (2025) Effect of risk management practices on the performance of ministries, departments and agencies (MDAs) in Nasarawa State, Nigeria. Anuk Coll Priv Sect Account J 2 (2): 44-56.

[33] Deepika MB, Kranti KM (2025) An integrated framework for risk management in procurement: Construction projects in India. Int J of Innov Technol Explor Eng 14 (3): 15-24. https://doi/10.35940/ijitee.B1046.14030225

How to cite this paper

Oso, S. B., Amiebenomo, M. I., Dedegu, U. I. "Impact of Risk Factors Associated with Procurement Process On Time Performance of Public Institutional Building Projects in Edo State, Nigeria" Iconic Research And Engineering Journals Volume 9 Issue 9 2026 Page 3185-3198 https://doi.org/10.64388/IREV9I9-1715786
Oso, S. B., Amiebenomo, M. I., Dedegu, U. I. "Impact of Risk Factors Associated with Procurement Process On Time Performance of Public Institutional Building Projects in Edo State, Nigeria" Iconic Research And Engineering Journals, vol. 9, no. 9, Mar. 2026, doi: https://doi.org/10.64388/IREV9I9-1715786
Oso, S. B., Amiebenomo, M. I., Dedegu, U. I. (2026). Impact of Risk Factors Associated with Procurement Process On Time Performance of Public Institutional Building Projects in Edo State, Nigeria. Iconic Research And Engineering Journals, 9(9). doi: https://doi.org/10.64388/IREV9I9-1715786
Oso, S. B., Amiebenomo, M. I., Dedegu, U. I. "Impact of Risk Factors Associated with Procurement Process On Time Performance of Public Institutional Building Projects in Edo State, Nigeria" Iconic Research And Engineering Journals, vol. 9, no. 9, Mar. 2026. Crossref, https://doi.org/10.64388/IREV9I9-1715786
@article{1715786,
      author = {Oso, S. B., Amiebenomo, M. I., Dedegu, U. I.},
      title = {Impact of Risk Factors Associated with Procurement Process On Time Performance of Public Institutional Building Projects in Edo State, Nigeria},
      journal = {Iconic Research And Engineering Journals},
      year = {2026},
      volume = {9},
      number = {9},
      pages = {3185-3198},
      issn = {2456-8880},
      url = {https://www.irejournals.com/formatedpaper/1715786.pdf},
      abstract = {Public construction projects in Edo State are frequently challenged by delays, which undermine project objectives, inflate costs and reduce stakeholder satisfaction. The study examines the impact of risk factors associated with procurement process on the time performance of public institutional building projects in Edo State, Nigeria. It identified a generic procurement process; the key risk factors associated with procurement process, the impact of risk factors on time performance, and propose strategies for mitigating risk factors associated with procurement process to improve time performance in selected public institutional building projects. A quantitative survey research design was adopted for the study; primary data were collected through structured questionnaires administered to construction professionals, procurement officers and contractors involved in public institutional projects in Edo State. Quantitative data were analysed using descriptive statistics and regression analysis to establish the strength and significance of relationship between risk factors and time performance. Results indicate that preparation of bidding documents and evaluation criteria were the most important procurement process and the most frequently occurring risks are fraud and corruption. Furthermore, the results reveal that there is a significant high relationship between risk factors associated with procurement process and time performance and comprehensive procurement planning and early risk assessment was identified as the most effective mitigating strategies.  The findings underscore the need for streamlined procurement procedures, enhanced capacity building for procurement professionals and the adoption of transparent and efficient contractor prequalification systems. The study concludes that mitigating procurement risk factors is essential to improve the timely delivery of public institutional building projects in Edo State   and recommends that there should be policy reforms and the implementation of best practices in public sector procurement to strength project time performance and enhances value for public investment.},
      keywords = {Procurement Process, Public Institutional Building Projects, Project Delays, Risk Factors, Time performance},
      month = {March},
      doi = {https://doi.org/10.64388/IREV9I9-1715786}
  }