Project Management Practices and Their Influence on the Timely Completion of Infrastructure Projects in DPWH Pampanga 2nd District Engineering Office

Pablo, Grachelle Ann B. Panahon, Kenneth L. Villar, Michael John M.

Subject area: Science,Engineering and Technology  ·  Area of research: Engineering Management

DOI: 10.64388/IREV9I10-1716286

Abstract

This study evaluates the effectiveness of project management practices and their direct influence on the timely completion of infrastructure projects at the DPWH Pampanga 2nd District Engineering Office. It is also the aim of this study to determine the specific levels of effectiveness across planning, execution, and monitoring phases, and identify the relationship between project management rigor and actual project timelines. Following a descriptive-quantitative research design, a structured survey questionnaire was utilized by this study to reveal perceptions among technical personnel regarding these management practices and project outcomes. The data collected was also analyzed to measure implementation levels and assess schedule adherence, efficiency, and excellence in project deliverables. Statistical tools, specifically weighted mean and Pearson’s correlation coefficient, were used to analyze the data. Results showed that monitoring and control practices achieved the highest level of perceived effectiveness with a mean score of 3.41, while a strong positive significant relationship (r = 0.7335) was attained between overall management rigor and timely completion. Moreover, data collected showed that Right-of-Way (ROW) coordination issues and daily monitoring of contractor equipment deployment were among the primary challenges encountered. Findings suggest that inadequate use of modern automated tracking tools and a reliance on traditional manual methods hinder maximizing operational efficiency and maximizing timely delivery across infrastructure projects.

Keywords

DPWH, Infrastructure, Project Management, Timely Completion

References

[1] Commission on Audit (COA). (2025). Annual Audit Report on the Department of Public Works and Highways.

[2] Dizon, V. (2026). "Fast-tracking of stalled infrastructure projects in Pampanga." Philippine Information Agency (PIA).

[3] Department of Public Works and Highways (DPWH). (2016). Department Order No. 193: Disqualification of Contractors with Negative Slippages.

[4] Ahmad, T., et al. (2018). "Review for Timely Completion of Infrastructure Projects." International Journal of Civil Engineering.

[5] Welde, M., & Klakegg, O. J. (2022). "Overcoming the unique challenges of project delays." ResearchGate.

[6] Philippine Researcher Study. (2025). "Cost and Time Overrun of Public Infrastructure Project in the Philippines: Inhibiting Factors." Journal of Construction Management.

[7] Vasantha Raju N., & Harinarayana, N.S. (2016, January). Online survey tools: A case study of Google Forms. Paper presented at the National Conference on "Scientific, Computational & Information Research Trends in Engineering, GSSS-IETW, Mysore.

[8] Dacanay, R., et al. (2023). Factors influencing the performance of Department of Public Works and Highways field engineers. Journal of Interdisciplinary Perspectives.

[9] Rivera, L., Baguec, H., & Yeom, C. (2020). A study on causes of delay in road construction projects across 25 developing countries. Infrastructures, 5(10), 84. https://

[10] Santos, A. (2019). Effective resource allocation and support systems in engineering projects. Philippine Engineering Review.

How to cite this paper

Pablo, Grachelle Ann B., Panahon, Kenneth L., Villar, Michael John M. "Project Management Practices and Their Influence on the Timely Completion of Infrastructure Projects in DPWH Pampanga 2nd District Engineering Office" Iconic Research And Engineering Journals Volume 9 Issue 10 2026 Page 1393-1400 https://doi.org/10.64388/IREV9I10-1716286
Pablo, Grachelle Ann B., Panahon, Kenneth L., Villar, Michael John M. "Project Management Practices and Their Influence on the Timely Completion of Infrastructure Projects in DPWH Pampanga 2nd District Engineering Office" Iconic Research And Engineering Journals, vol. 9, no. 10, Apr. 2026, doi: https://doi.org/10.64388/IREV9I10-1716286
Pablo, Grachelle Ann B., Panahon, Kenneth L., Villar, Michael John M. (2026). Project Management Practices and Their Influence on the Timely Completion of Infrastructure Projects in DPWH Pampanga 2nd District Engineering Office. Iconic Research And Engineering Journals, 9(10). doi: https://doi.org/10.64388/IREV9I10-1716286
Pablo, Grachelle Ann B., Panahon, Kenneth L., Villar, Michael John M. "Project Management Practices and Their Influence on the Timely Completion of Infrastructure Projects in DPWH Pampanga 2nd District Engineering Office" Iconic Research And Engineering Journals, vol. 9, no. 10, Apr. 2026. Crossref, https://doi.org/10.64388/IREV9I10-1716286
@article{1716286,
      author = {Pablo, Grachelle Ann B., Panahon, Kenneth L., Villar, Michael John M.},
      title = {Project Management Practices and Their Influence on the Timely Completion of Infrastructure Projects in DPWH Pampanga 2nd District Engineering Office},
      journal = {Iconic Research And Engineering Journals},
      year = {2026},
      volume = {9},
      number = {10},
      pages = {1393-1400},
      issn = {2456-8880},
      url = {https://www.irejournals.com/formatedpaper/1716286.pdf},
      abstract = {This study evaluates the effectiveness of project management practices and their direct influence on the timely completion of infrastructure projects at the DPWH Pampanga 2nd District Engineering Office. It is also the aim of this study to determine the specific levels of effectiveness across planning, execution, and monitoring phases, and identify the relationship between project management rigor and actual project timelines. Following a descriptive-quantitative research design, a structured survey questionnaire was utilized by this study to reveal perceptions among technical personnel regarding these management practices and project outcomes. The data collected was also analyzed to measure implementation levels and assess schedule adherence, efficiency, and excellence in project deliverables. Statistical tools, specifically weighted mean and Pearson’s correlation coefficient, were used to analyze the data. Results showed that monitoring and control practices achieved the highest level of perceived effectiveness with a mean score of 3.41, while a strong positive significant relationship (r = 0.7335) was attained between overall management rigor and timely completion. Moreover, data collected showed that Right-of-Way (ROW) coordination issues and daily monitoring of contractor equipment deployment were among the primary challenges encountered. Findings suggest that inadequate use of modern automated tracking tools and a reliance on traditional manual methods hinder maximizing operational efficiency and maximizing timely delivery across infrastructure projects.},
      keywords = {DPWH, Infrastructure, Project Management, Timely Completion},
      month = {April},
      doi = {https://doi.org/10.64388/IREV9I10-1716286}
  }