Assessment of Factors Affecting Cost Management in Low Cost Housing Project Delivery in Ebonyi State

Ibiyemi Mutiu Tolani Chukwuemeka Ngwu Nwobu Ifeanyichukwu Chukwunonso Eze Gideon Chigozie

Subject area: Science,Engineering and Technology  ·  Area of research: Cost Management

DOI: 10.64388/IREV9I12-1719308

Abstract

This study assessed the factors affecting cost management and the challenges hindering effective cost control in low-cost housing project delivery in Ebonyi State, Nigeria. A descriptive survey research design was adopted, and data were collected from 278 construction professionals, including quantity surveyors, architects, builders, engineers, project managers, and contractors. Data were analyzed using mean score, standard deviation and ranking techniques. The findings revealed that fluctuations in construction materials prices, poor supervision and site management,ineffective communication among stakeholders, inflation, inaccurate cost estimation, and inadequate funding are the major factors affecting cost management in low-cost housing projects. The study further found that delayed release of project funds, inflation, inadequate cost monitoring systems, and frequent design changes are the major challenges hindering effective cost management. The study concludes that effective planning, proper financial management, continuous cost monitoring, and stakeholder collaboration are essential for improving cost performance and enhancing affordable housing delivery in Ebonyi State.

Keywords

Cost Management, Cost Control, Low-Cost Housing, Housing Project Delivery, Construction Industry, Ebonyi State

References

[1] Obi LI, Arif M, Kulonda DJ (2017) Prioritizing cost management system considerations for Nigerian housing projects. J finanmanag prop const, 22 (2):135-153

[2] Oguchi OK, Habu I (2024) Examining the relationship between poor health and safety management practices and building construction project delivery: A case study of Ebonyi State. J of BuiEnv Geo Res, 12 (1): 45-58.

[3] Gupta, JK (2022) Roles and Importance of Housing. https://www.linkedin.com/pulse/role-importance-housing-jit-kumar-gupta/

[4] Adedeji, I, Deveci, G, Salman, H (2023) The Challenges in Providing Affordable Housing in Nigeria and the Adequate Sustainable Approaches for Addressing Them. Open Journal of Applied Science. Scott Sutherland School of Architecture and Built Environment, Robert Gordon University, Aberdeen, UK. Vol.13, No.3.Doi: 10.4236/ojapps.2023.133035.

[5] Ogbu CP, Adindu C.C (2012) Project management approach to public low-income housing delivery in Nigeria. J ResNat Dev, 10 (2): 142-153

[6] Gopalan, Venkataman M (2015) Affordable housing: policy and practice in India. IIBM Manag Rev, 27 (2): 129-140

[7] Assaf SA, Al-Hejji S. (2006) Causes of delay in large construction projects. Int J Pro Manag, 24 (4):349-357.

[8] Ubani EC, Okorocha KA, Emenbe SC (2013) Analysis of factors influencing time and cost overruns on construction projects in South Eastern Nigeria. Int J ManagSci Bus Res2 (2): 54-63

[9] MemonH, Rahman IA, Abdullah MR, Ais AAA (2014) Factors affecting construction cost performance in project management projects. Case of Mara large projects. Intl CivEng and Bui Env 1 (1): 30-35.

[10] Arif M, Egbu CO, Toma T (2010) Knowledge retention in construction in the UAE in Egbu (ed) proceedings of the 26th Annual ARCOM Conference vol 2, pp 887-896. Association of Researchers in Construction Management (ARCOM)

[11] Smith, P (2014) Project Cost Management – Global Issues and Challenges. Procedia - Social and Behavioral Sciences, 119, 485-494. doi: 10.1016/j.sbspro.2014.03.054

[12] Edison JC (2025) Do sustainability initiatives cause delays and cost overruns in construction. J of Inform Edu and Res, 5 (1): 966-984.

[13] Ajayi TO, Daramola OT, Adhuze OO (2024) cost management evolution in building projects. A review of innovations and challenges. Int J of ResInnov App Sci, 9 (9): 80-95

[14] Afana O, Al Zubaidi R, Abu Dabous S, Ibrahim F 2024. Categories and factors of cost overrun in construction projects: A systematic review. EngTechAppSci Res, 14 (6): 18330-18347.

[15] Obi L I, Arif M, Goulding J (2020) Low-cost housing: A cost management model for process integration and evaluation. Arch Eng Des Manag, 16 (6): 431-448.

[16] Okonkwo C, Evans UF, Ekunga S (2023) Unearthing direct and indirect material waste related factors underpinning cost overruns in construction projects. Int Journal ConstManag, 23 (13): 2298-2304

How to cite this paper

Ibiyemi Mutiu Tolani, Chukwuemeka Ngwu, Nwobu Ifeanyichukwu Chukwunonso, Eze Gideon Chigozie "Assessment of Factors Affecting Cost Management in Low Cost Housing Project Delivery in Ebonyi State" Iconic Research And Engineering Journals Volume 9 Issue 12 2026 Page 3253-3260 https://doi.org/10.64388/IREV9I12-1719308
Ibiyemi Mutiu Tolani, Chukwuemeka Ngwu, Nwobu Ifeanyichukwu Chukwunonso, Eze Gideon Chigozie "Assessment of Factors Affecting Cost Management in Low Cost Housing Project Delivery in Ebonyi State" Iconic Research And Engineering Journals, vol. 9, no. 12, Jun. 2026, doi: https://doi.org/10.64388/IREV9I12-1719308
Ibiyemi Mutiu Tolani, Chukwuemeka Ngwu, Nwobu Ifeanyichukwu Chukwunonso, Eze Gideon Chigozie (2026). Assessment of Factors Affecting Cost Management in Low Cost Housing Project Delivery in Ebonyi State. Iconic Research And Engineering Journals, 9(12). doi: https://doi.org/10.64388/IREV9I12-1719308
Ibiyemi Mutiu Tolani, Chukwuemeka Ngwu, Nwobu Ifeanyichukwu Chukwunonso, Eze Gideon Chigozie "Assessment of Factors Affecting Cost Management in Low Cost Housing Project Delivery in Ebonyi State" Iconic Research And Engineering Journals, vol. 9, no. 12, Jun. 2026. Crossref, https://doi.org/10.64388/IREV9I12-1719308
@article{1719308,
      author = {Ibiyemi Mutiu Tolani, Chukwuemeka Ngwu, Nwobu Ifeanyichukwu Chukwunonso, Eze Gideon Chigozie},
      title = {Assessment of Factors Affecting Cost Management in Low Cost Housing Project Delivery in Ebonyi State},
      journal = {Iconic Research And Engineering Journals},
      year = {2026},
      volume = {9},
      number = {12},
      pages = {3253-3260},
      issn = {2456-8880},
      url = {https://www.irejournals.com/formatedpaper/1719308.pdf},
      abstract = {This study assessed the factors affecting cost management and the challenges hindering effective cost control in low-cost housing project delivery in Ebonyi State, Nigeria. A descriptive survey research design was adopted, and data were collected from 278 construction professionals, including quantity surveyors, architects, builders, engineers, project managers, and contractors. Data were analyzed using mean score, standard deviation and ranking techniques. The findings revealed that fluctuations in construction materials prices, poor supervision and site management,ineffective communication among stakeholders, inflation, inaccurate cost estimation, and inadequate funding are the major factors affecting cost management in low-cost housing projects. The study further found that delayed release of project funds, inflation, inadequate cost monitoring systems, and frequent design changes are the major challenges hindering effective cost management. The study concludes that effective planning, proper financial management, continuous cost monitoring, and stakeholder collaboration are essential for improving cost performance and enhancing affordable housing delivery in Ebonyi State.},
      keywords = {Cost Management, Cost Control, Low-Cost Housing, Housing Project Delivery, Construction Industry, Ebonyi State},
      month = {June},
      doi = {https://doi.org/10.64388/IREV9I12-1719308}
  }