Predictive Analytics for Construction Material Procurement, Cost Control and Schedule Performance in Saudi Giga-Projects

Mohammed Shebin

Subject area: Science,Engineering and Technology  ·  Area of research: Predictive Analytics

Abstract

Unprecedented construction activity, tight delivery windows, complex interfaces, global sourcing, and exposure to volatile material markets characterize Saudi Arabia’s giga-project portfolio. These conditions make procurement, cost control, and schedule performance highly interrelated. This review critically discusses how predictive analytics can convert fragmented project, commercial, supply-chain, and progress data into forward-looking decisions for construction material procurement for Saudi giga-projects. An integrative review method integrates recent peer-reviewed evidence on machine learning, construction cost forecasting, schedule prediction, digital supply chains, building information modeling, digital twins, and Saudi project performance. The literature indicates that the predictive value is greatest when models combine material demand, price escalation, supplier reliability, lead times, inventory status, progress quantities, and schedule logic, rather than attempting to predict a single outcome in isolation. Ensemble learning and hybrid models regularly yield better forecasting precision, but their operational-level usefulness depends on data quality, temporal validity, explainability, and integration with procurement and project-control workflows. Saudi studies consistently identify material-price fluctuation, change orders, planning weaknesses, and delayed approvals as major cost and time pressures. Yet, direct evidence of analytics-enabled procurement in giga-project settings remains limited. The review suggests an integrated predictive-control architecture that links 5D BIM, enterprise resource planning, supplier data, market indicators and planning systems. It argues that predictive analytics in giga-project organizations should be seen as a governance capability rather than a standalone algorithm, marrying model outputs with human review, uncertainty ranges and auditable intervention thresholds. Future research directions encompass Saudi longitudinal datasets, cross-project transferability, causal evaluation of interventions, supplier-risk prediction, and explainable models that jointly optimize procurement cost, material availability, and schedule resilience.

Keywords

predictive analytics; construction procurement; material price forecasting; cost control; schedule performance; Saudi Arabia; giga-projects; BIM; digital twins; machine learning

References

[1] Abioye SO, Oyedele LO, Akanbi L, Ajayi A, Davila Delgado JM, Bilal M, et al. (2021). Artificial intelligence in the construction industry: A review of present status, opportunities and future challenges. Journal of Building Engineering, 44, 103299. https://doi.org/10.1016/j.jobe.2021.103299

[2] Alasmari E, Martinez-Vazquez P, Baniotopoulos C (2023). An analysis of the qualitative impacts of Building Information Modelling (BIM) on life cycle cost (LCC): A qualitative case study of the KSA. Buildings, 13(8), 2071. https://doi.org/10.3390/buildings13082071

[3] Aldossari KM (2025). Cost and schedule performance in higher education construction projects in Saudi Arabia. Advances in Civil Engineering, 2025, 7448384. https://doi.org/10.1155/adce/7448384

[4] Alfalah G, Aldajani S, Elshaboury N, Al-Sakkaf A, Alshamrani O (2024). Development of a performance assessment model for contractors in Saudi Arabian construction projects. Advances in Civil Engineering, 2024, 8780539. https://doi.org/10.1155/2024/8780539

[5] Algahtany M, Radzi AR, Al-Mohammad MS, Rahman RA (2023). Government initiatives for enhancing Building Information Modeling adoption in Saudi Arabia. Buildings, 13(9), 2130. https://doi.org/10.3390/buildings13092130

[6] Alghuried A (2023). Measuring the benefits and barriers of the implementation of BIM in sustainable practice in the construction industry of Saudi Arabia. Sustainability, 15(19), 14323. https://doi.org/10.3390/su151914323

[7] Alnaser AA, Alsanabani NM, Al-Gahtani KS (2023). BIM impact on construction project time using system dynamics in Saudi Arabia’s construction. Buildings, 13(9), 2267. https://doi.org/10.3390/buildings13092267

[8] Alotaibi R, Sohail M, Soetanto R (2025). Modelling project control system effectiveness in Saudi Arabian construction project delivery. Buildings, 15(18), 3426. https://doi.org/10.3390/buildings15183426

[9] Alshihri S, Al-Gahtani K, Almohsen A (2022). Risk factors that lead to time and cost overruns of building projects in Saudi Arabia. Buildings, 12(7), 902. https://doi.org/10.3390/buildings12070902

[10] Almujibah H (2023). Assessment of Building Information Modeling (BIM) as a time and cost-saving construction management tool: Evidence from two-story villas in Jeddah. Sustainability, 15(9), 7354. https://doi.org/10.3390/su15097354

[11] Amer F, Hockenmaier J, Golparvar-Fard M (2022). Learning and critiquing pairwise activity relationships for schedule quality control via deep learning-based natural language processing. Automation in Construction, 134, 104036. https://doi.org/10.1016/j.autcon.2021.104036

[12] Amer F, Jung Y, Golparvar-Fard M (2023). Construction schedule augmentation with implicit dependency constraints and automated generation of lookahead plan revisions. Automation in Construction, 152, 104896. https://doi.org/10.1016/j.autcon.2023.104896

[13] Baduge SK, Thilakarathna S, Perera JS, Arashpour M, Sharafi P, Teodosio B, et al. (2022). Artificial intelligence and smart vision for building and construction 4.0: Machine and deep learning methods and applications. Automation in Construction, 141, 104440. https://doi.org/10.1016/j.autcon.2022.104440

[14] Bakhshi R, Fard Moradinia S, Jani R, Vafaei Poor R (2022). Presenting a hybrid scheme of machine learning combined with metaheuristic optimizers for predicting final cost and time of project. KSCE Journal of Civil Engineering, 26(8), 3188–3203. https://doi.org/10.1007/s12205-022-1424-3

[15] Chen Z, Hammad AWA, Waller ST, Haddad AN (2023). Modelling supplier selection and material purchasing for the construction supply chain in a fuzzy scenario-based environment. Automation in Construction, 150, 104847. https://doi.org/10.1016/j.autcon.2023.104847

[16] Egwim CN, Alaka H, Toriola-Coker LO, Balogun H, Sunmola F (2021). Applied artificial intelligence for predicting construction projects delay. Machine Learning with Applications, 6, 100166. https://doi.org/10.1016/j.mlwa.2021.100166

[17] Lee D, Lee S (2021). Digital twin for supply chain coordination in modular construction. Applied Sciences, 11(13), 5909. https://doi.org/10.3390/app11135909

[18] Lederer L, Ellingerová H, Ďubek S, Bočkaj J, Ďubek M (2024). Construction price forecasting models in the construction industry: A comparative analysis. Buildings, 14(5), 1325. https://doi.org/10.3390/buildings14051325

[19] Liu Q, He P, Peng S, Wang T, Ma J (2024). A survey of data-driven construction materials price forecasting. Buildings, 14(10), 3156. https://doi.org/10.3390/buildings14103156

[20] Meharie MG, Mengesha WJ, Gariy Z, Mutuku RN (2022). Application of stacking ensemble machine learning algorithm in predicting the cost of highway construction projects. Engineering, Construction and Architectural Management, 29(7), 2836–2853. https://doi.org/10.1108/ECAM-02-2020-0128

[21] Mohsen O, Mohamed Y, Al-Hussein M (2022). A machine learning approach to predict production time using real-time RFID data in industrialized building construction. Advanced Engineering Informatics, 52, 101631. https://doi.org/10.1016/j.aei.2022.101631

[22] Mosly I (2025). Multivariate analysis of factors influencing construction costs in Saudi Arabia. Buildings, 15(5), 687. https://doi.org/10.3390/buildings15050687

[23] Omrany H, Al-Obaidi KM, Husain A, Ghaffarianhoseini A (2023). Digital twins in the construction industry: A comprehensive review of current implementations, enabling technologies, and future directions. Sustainability, 15(14), 10908. https://doi.org/10.3390/su151410908

[24] Regona M, Yigitcanlar T, Xia B, Li RYM (2022). Opportunities and adoption challenges of AI in the construction industry: A PRISMA review. Journal of Open Innovation: Technology, Market, and Complexity, 8(1), 45. https://doi.org/10.3390/joitmc8010045

[25] Ranjbar AA, Ansari R, Taherkhani R, Hosseini MR (2021). Developing a novel cash flow risk analysis framework for construction projects based on 5D BIM. Journal of Building Engineering, 44, 103341. https://doi.org/10.1016/j.jobe.2021.103341

[26] Sharma V, Zaki M, Jha KN, Krishnan NMA (2022). Machine learning-aided cost prediction and optimization in construction operations. Engineering, Construction and Architectural Management, 29(3), 1241–1257. https://doi.org/10.1108/ECAM-10-2020-0778

[27] Shiha A, El-adaway IH (2024). Forecasting construction material prices using macroeconomic indicators of trading partners. Journal of Management in Engineering, 40(5). https://doi.org/10.1061/JMENEA.MEENG-6106

[28] Studer WP, de Brito Mello LCB (2021). Core elements underlying supply chain management in the construction industry: A systematic literature review. Buildings, 11(12), 569. https://doi.org/10.3390/buildings11120569

[29] Yevu SK, Yu ATW, Darko A (2021). Digitalization of construction supply chain and procurement in the built environment: Emerging technologies and opportunities for sustainable processes. Journal of Cleaner Production, 322, 129093. https://doi.org/10.1016/j.jclepro.2021.129093

[30] Yoon JH, Pishdad-Bozorgi P (2022). State-of-the-art review of blockchain-enabled construction supply chain. Journal of Construction Engineering and Management, 148(2). https://doi.org/10.1061/(ASCE)CO.1943-7862.0002235

How to cite this paper

Mohammed Shebin "Predictive Analytics for Construction Material Procurement, Cost Control and Schedule Performance in Saudi Giga-Projects" Iconic Research And Engineering Journals Volume 10 Issue 4 2026 Page 1584-1597
Mohammed Shebin "Predictive Analytics for Construction Material Procurement, Cost Control and Schedule Performance in Saudi Giga-Projects" Iconic Research And Engineering Journals, vol. 10, no. 4, Oct. 2026
Mohammed Shebin (2026). Predictive Analytics for Construction Material Procurement, Cost Control and Schedule Performance in Saudi Giga-Projects. Iconic Research And Engineering Journals, 10(4).
Mohammed Shebin "Predictive Analytics for Construction Material Procurement, Cost Control and Schedule Performance in Saudi Giga-Projects" Iconic Research And Engineering Journals, vol. 10, no. 4, Oct. 2026.
@article{1723910,
      author = {Mohammed Shebin},
      title = {Predictive Analytics for Construction Material Procurement, Cost Control and Schedule Performance in Saudi Giga-Projects},
      journal = {Iconic Research And Engineering Journals},
      year = {2026},
      volume = {10},
      number = {4},
      pages = {1584-1597},
      issn = {2456-8880},
      url = {https://www.irejournals.com/formatedpaper/1723910.pdf},
      abstract = {Unprecedented construction activity, tight delivery windows, complex interfaces, global sourcing, and exposure to volatile material markets characterize Saudi Arabia’s giga-project portfolio. These conditions make procurement, cost control, and schedule performance highly interrelated. This review critically discusses how predictive analytics can convert fragmented project, commercial, supply-chain, and progress data into forward-looking decisions for construction material procurement for Saudi giga-projects. An integrative review method integrates recent peer-reviewed evidence on machine learning, construction cost forecasting, schedule prediction, digital supply chains, building information modeling, digital twins, and Saudi project performance. The literature indicates that the predictive value is greatest when models combine material demand, price escalation, supplier reliability, lead times, inventory status, progress quantities, and schedule logic, rather than attempting to predict a single outcome in isolation. Ensemble learning and hybrid models regularly yield better forecasting precision, but their operational-level usefulness depends on data quality, temporal validity, explainability, and integration with procurement and project-control workflows. Saudi studies consistently identify material-price fluctuation, change orders, planning weaknesses, and delayed approvals as major cost and time pressures. Yet, direct evidence of analytics-enabled procurement in giga-project settings remains limited. The review suggests an integrated predictive-control architecture that links 5D BIM, enterprise resource planning, supplier data, market indicators and planning systems. It argues that predictive analytics in giga-project organizations should be seen as a governance capability rather than a standalone algorithm, marrying model outputs with human review, uncertainty ranges and auditable intervention thresholds. Future research directions encompass Saudi longitudinal datasets, cross-project transferability, causal evaluation of interventions, supplier-risk prediction, and explainable models that jointly optimize procurement cost, material availability, and schedule resilience.},
      keywords = {predictive analytics; construction procurement; material price forecasting; cost control; schedule performance; Saudi Arabia; giga-projects; BIM; digital twins; machine learning},
      month = {October},
  }