Project Initiation Processes and Public Building Project Delivery in South-West Nigeria: A Cross-Sectional Study
Subject area: Science,Engineering and Technology · Area of research: Construction Management Technology
Abstract
Public building projects in South-West Nigeria continue to encounter delays, cost pressure, quality concerns and abandonment, raising questions about the adequacy of project decisions made before execution. This study assessed the association between project initiation processes and public building project delivery. A cross-sectional survey targeted 402 building professionals drawn from a population of 480 across six South-West states. Of 402 questionnaires administered, 305 were retrieved (75.9%) and 300 were suitable for analysis (74.6% of those distributed). Descriptive statistics, multiple regression and seemingly unrelated regression (SUR) were used. Mean agreement scores were 4.262 for project charter development, 4.060 for stakeholder identification, 4.163 for feasibility studies and 4.210 for project team assembly; the initiation composite was 4.174 (SD = 0.735). The overall delivery regression was significant, F(4, 295) = 40.451, p < .001, R² = .354. In separate SUR equations, the initiation factors were jointly associated with cost (Wald χ² = 78.70), time (94.86) and quality (104.29), each p < .001. However, several individual coefficients were not significant, indicating that effects varied by outcome. Stronger initiation arrangements were associated with more favourable perceived building delivery, although the cross-sectional design does not establish causality. Public project sponsors should formalise project charters, stakeholder assessment, feasibility appraisal and team selection before authorising construction.
Keywords
Project initiation, public building projects, project charter, stakeholder identification, project delivery, South-West Nigeria
References
[1] Anthony GA (2018). Project initiation process, monitoring and evaluation team capacity, compliance with legal framework and building project success: The case of building projects in Roysambu Constituency, Nairobi County, Kenya. Antidotes Journal of Social Sciences, 3(3), 106–116.
[2] Freeman RE (1984). Strategic Management: A Stakeholder Approach. Boston: Pitman.
[3] Mutwiri FR, Were S, Odhiambo R (2018). Project identification and initiation practices on the success of CDF construction projects in Kenya. Journal of Entrepreneurship & Project Management, 2(2), 47–56.
[4] Oladipo FO, Ojo OJ, Abayomi A, Lawala F (2024). Beneficiaries of frugal practices and public building projects delivery in Southwest, Nigeria. International Journal of Civil Engineering, Construction and Estate Management, 12(2), 22–43.
[5] Olanrewaju AA, Akinradewo DF, Oyedele LO (2022). Challenges of public building projects in Nigeria. Journal of Building Engineering, 45, 103622.
[6] Project Management Institute (2021). A Guide to the Project Management Body of Knowledge (PMBOK Guide) (7th ed.). Newtown Square, PA: Project Management Institute.
[7] Ratanya MD, Lucy N (2023). Influence of project initiation on project performance among infrastructure projects in Meru County, Kenya. International Journal of Management and Commerce Innovations, 10.
[8] Usman NK, Kamau PK, Mireri C (2014). The impact of initiation phase principles on project performance within the building industry in Abuja, Nigeria. American International Journal of Contemporary Research, 4(7).
How to cite this paper
@article{1724999,
author = {Ogunsemore, O. S., Alade, K. T., Sunday, O. G., Ekundayo, K. J.},
title = {Project Initiation Processes and Public Building Project Delivery in South-West Nigeria: A Cross-Sectional Study},
journal = {Iconic Research And Engineering Journals},
year = {2026},
volume = {10},
number = {5},
pages = {3271-3279},
issn = {2456-8880},
url = {https://www.irejournals.com/formatedpaper/1724999.pdf},
abstract = {Public building projects in South-West Nigeria continue to encounter delays, cost pressure, quality concerns and abandonment, raising questions about the adequacy of project decisions made before execution. This study assessed the association between project initiation processes and public building project delivery. A cross-sectional survey targeted 402 building professionals drawn from a population of 480 across six South-West states. Of 402 questionnaires administered, 305 were retrieved (75.9%) and 300 were suitable for analysis (74.6% of those distributed). Descriptive statistics, multiple regression and seemingly unrelated regression (SUR) were used. Mean agreement scores were 4.262 for project charter development, 4.060 for stakeholder identification, 4.163 for feasibility studies and 4.210 for project team assembly; the initiation composite was 4.174 (SD = 0.735). The overall delivery regression was significant, F(4, 295) = 40.451, p < .001, R² = .354. In separate SUR equations, the initiation factors were jointly associated with cost (Wald χ² = 78.70), time (94.86) and quality (104.29), each p < .001. However, several individual coefficients were not significant, indicating that effects varied by outcome. Stronger initiation arrangements were associated with more favourable perceived building delivery, although the cross-sectional design does not establish causality. Public project sponsors should formalise project charters, stakeholder assessment, feasibility appraisal and team selection before authorising construction.},
keywords = {Project initiation, public building projects, project charter, stakeholder identification, project delivery, South-West Nigeria},
month = {November},
}