Machine Learning for Construction Delay Prediction in Saudi Arabian Mega-Projects: A Structured Review and Research Agenda Aligned with Vision 2030

Ahmed Babu Shahas V P

Subject area: Science,Engineering and Technology  ·  Area of research: Digital Construction Delay Analysis

Abstract

Saudi Arabia's Vision 2030 has created one of the largest construction programmes in the world, and delivering it on time is a national priority. Schedule delay has nevertheless been a persistent feature of the Kingdom's construction sector for four decades. Machine learning (ML) offers a way to move from explaining delays after they occur to predicting them while there is still time to act. This paper presents a structured review of published work on ML-based construction delay prediction and of the evidence on delay causes in Saudi Arabia, and derives a research agenda for Saudi mega-projects. The review finds that the causes of delay in the Kingdom are well documented and stable over time, with payment, change-order, planning and workforce factors recurring across studies. ML studies report classification accuracies above 90%, but most are trained on small, questionnaire-derived datasets, are validated internally only, and predict a single static outcome for conventional projects. Only a small number use Saudi project records, and none of the reviewed studies addresses giga-project scale. Seven research priorities are proposed, covering shared project-outcome data, time-dependent prediction from progress records, external validation, explainable models, programme-level interdependence, text-based data sources and the link from prediction to mitigation. Each priority is mapped to the objectives of Vision 2030.

Keywords

construction delay, machine learning, mega-projects, Saudi Arabia, Vision 2030

References

[1] Kingdom of Saudi Arabia. Vision 2030 [Internet]. Riyadh: Kingdom of Saudi Arabia; 2016 [cited 2026 Nov 12]. Available from: https://www.vision2030.gov.sa

[2] Varghese J. Delayed delivery of global megaprojects may wipe $1.5 trillion off world economy by 2030. Gulf News [Internet]. 2025 Jul [cited 2026 Nov 12]. Available from: https://gulfnews.com

[3] Flyvbjerg B. What you should know about megaprojects and why: An overview. Project Management Journal. 2014;45(2):6–19.

[4] Assaf SA, Al-Hejji S. Causes of delay in large construction projects. International Journal of Project Management. 2006;24(4):349–357.

[5] Al-Kharashi A, Skitmore M. Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics. 2009;27(1):3–23.

[6] Alshihri S, Al-Gahtani K, Almohsen A. Risk factors that lead to time and cost overruns of building projects in Saudi Arabia. Buildings. 2022;12(7):902.

[7] Gondia A, Siam A, El-Dakhakhni W, Nassar AH. Machine learning algorithms for construction projects delay risk prediction. Journal of Construction Engineering and Management. 2020;146(1):04019085.

[8] Yaseen ZM, Ali ZH, Salih SQ, Al-Ansari N. Prediction of risk delay in construction projects using a hybrid artificial intelligence model. Sustainability. 2020;12(4):1514.

[9] Egwim CN, Alaka H, Toriola-Coker LO, Balogun H, Sunmola F. Applied artificial intelligence for predicting construction projects delay. Machine Learning with Applications. 2021;6:100166.

[10] Darko A, Chan APC, Adabre MA, Edwards DJ, Hosseini MR, Ameyaw EE. Artificial intelligence in the AEC industry: Scientometric analysis and visualization of research activities. Automation in Construction. 2020;112:103081.

[11] Pan Y, Zhang L. Roles of artificial intelligence in construction engineering and management: A critical review and future trends. Automation in Construction. 2021;122:103517.

[12] Gao Y, Antwi-Afari MF, Huang Y, Chen ZS, Manzoor B. Artificial intelligence in construction project management: A systematic literature review of cost, time, and safety management. Buildings. 2026;16(5):1061.

[13] Bageis AS. An investigation into the causes of payment delays and deliberate delay tactics in public construction projects in Saudi Arabia. Buildings. 2024;14(6):1792.

[14] Alsugair AM, Al-Gahtani KS, Alsanabani NM, Alabduljabbar AA, Almohsen AS. Artificial neural network model to predict final construction contract duration. Applied Sciences. 2023;13(14):8078.

[15] Assaf SA, Al-Khalil M, Al-Hazmi M. Causes of delay in large building construction projects. Journal of Management in Engineering. 1995;11(2):45–50.

[16] Al-Khalil MI, Al-Ghafly MA. Important causes of delay in public utility projects in Saudi Arabia. Construction Management and Economics. 1999;17(5):647–655.

[17] Mahamid I. Contributors to schedule delays in public construction projects in Saudi Arabia: Owners' perspective. Journal of Construction Project Management and Innovation. 2013;3(2):608–619.

[18] Alajmi AM, Memon ZA. A review on significant factors causing delays in Saudi Arabia construction projects. Smart Cities. 2022;5(4):1465–1487.

[19] Sanni-Anibire MO, Zin RM, Olatunji SO. Causes of delay in the global construction industry: A meta analytical review. International Journal of Construction Management. 2022;22(8):1395–1407.

[20] Sanni-Anibire MO, Zin RM, Olatunji SO. Machine learning model for delay risk assessment in tall building projects. International Journal of Construction Management. 2022;22(11):2134–2143.

[21] Sanni-Anibire M, Zin R, Olatunji S. Forecasting construction delay times in high-rise building projects. In: Proceedings of International Structural Engineering and Construction (EURO-MED-SEC-3). ISEC Press; 2020, paper CON-16.

[22] Al-Bataineh F, Khatatbeh AA, Alzubi Y. Unsupervised machine learning for identifying key risk factors contributing to construction delays. Organization, Technology and Management in Construction. 2024;16:170–185.

[23] Wauters M, Vanhoucke M. Support vector machine regression for project control forecasting. Automation in Construction. 2014;47:92–106.

[24] Breiman L. Random forests. Machine Learning. 2001;45(1):5–32.

[25] Chen T, Guestrin C. XGBoost: A scalable tree boosting system. In: Proceedings of the 22nd ACM SIGKDD International Conference on Knowledge Discovery and Data Mining. 2016:785–794.

[26] Maurya S, Lakkimsetty NR. Balancing accuracy and interpretability: AI-driven predictive modeling of construction schedule performance in India. Asian Journal of Civil Engineering. 2025;26(7).

[27] Cho M, et al. From prediction to prioritization: Automated framework for delay risk management in highway earthwork projects. Automation in Construction. 2026;181:106588.

[28] Shirazi DH, Toosi H. Deep multilayer perceptron neural network for the prediction of Iranian dam project delay risks. Journal of Construction Engineering and Management. 2023;149(4). https://doi.org/10.1061/JCEMD4.COENG-12367

[29] Egwim CN, Alaka H. A comparative study on machine learning algorithms for predicting construction projects delay. In: Proceedings of the Environmental Design and Management International Conference (EDMIC). Bristol, U.K.; 2021.

[30] Hochreiter S, Schmidhuber J. Long short-term memory. Neural Computation. 1997;9(8):1735–1780.

[31] Lundberg SM, Lee SI. A unified approach to interpreting model predictions. In: Advances in Neural Information Processing Systems 30. 2017:4765–4774.

[32] Egwim CN, et al. Systematic review of critical drivers for delay risk prediction: Towards a conceptual framework for BIM-based construction projects. Frontiers in Engineering and Built Environment. 2023;3(1):16–31.

[33] Sanni-Anibire MO, Zin RM, Olatunji SO. Machine learning-based framework for construction delay mitigation. Journal of Information Technology in Construction (ITcon). 2021;26:303–318.

[34] Alotaibi R. Determinants of project control system effectiveness in Saudi Arabian construction project delivery [dissertation]. Loughborough (UK): Loughborough University; 2025.

[35] Alaboud N, Alshahrani A. Adoption of building information modelling in the Saudi construction industry: An interpretive structural modelling. Sustainability. 2023;15(7):6130.

How to cite this paper

Ahmed Babu Shahas V P "Machine Learning for Construction Delay Prediction in Saudi Arabian Mega-Projects: A Structured Review and Research Agenda Aligned with Vision 2030" Iconic Research And Engineering Journals Volume 10 Issue 5 2026 Page 2530-2539
Ahmed Babu Shahas V P "Machine Learning for Construction Delay Prediction in Saudi Arabian Mega-Projects: A Structured Review and Research Agenda Aligned with Vision 2030" Iconic Research And Engineering Journals, vol. 10, no. 5, Nov. 2026
Ahmed Babu Shahas V P (2026). Machine Learning for Construction Delay Prediction in Saudi Arabian Mega-Projects: A Structured Review and Research Agenda Aligned with Vision 2030. Iconic Research And Engineering Journals, 10(5).
Ahmed Babu Shahas V P "Machine Learning for Construction Delay Prediction in Saudi Arabian Mega-Projects: A Structured Review and Research Agenda Aligned with Vision 2030" Iconic Research And Engineering Journals, vol. 10, no. 5, Nov. 2026.
@article{1725104,
      author = {Ahmed Babu Shahas V P},
      title = {Machine Learning for Construction Delay Prediction in Saudi Arabian Mega-Projects: A Structured Review and Research Agenda Aligned with Vision 2030},
      journal = {Iconic Research And Engineering Journals},
      year = {2026},
      volume = {10},
      number = {5},
      pages = {2530-2539},
      issn = {2456-8880},
      url = {https://www.irejournals.com/formatedpaper/1725104.pdf},
      abstract = {Saudi Arabia's Vision 2030 has created one of the largest construction programmes in the world, and delivering it on time is a national priority. Schedule delay has nevertheless been a persistent feature of the Kingdom's construction sector for four decades. Machine learning (ML) offers a way to move from explaining delays after they occur to predicting them while there is still time to act. This paper presents a structured review of published work on ML-based construction delay prediction and of the evidence on delay causes in Saudi Arabia, and derives a research agenda for Saudi mega-projects. The review finds that the causes of delay in the Kingdom are well documented and stable over time, with payment, change-order, planning and workforce factors recurring across studies. ML studies report classification accuracies above 90%, but most are trained on small, questionnaire-derived datasets, are validated internally only, and predict a single static outcome for conventional projects. Only a small number use Saudi project records, and none of the reviewed studies addresses giga-project scale. Seven research priorities are proposed, covering shared project-outcome data, time-dependent prediction from progress records, external validation, explainable models, programme-level interdependence, text-based data sources and the link from prediction to mitigation. Each priority is mapped to the objectives of Vision 2030.},
      keywords = {construction delay, machine learning, mega-projects, Saudi Arabia, Vision 2030},
      month = {November},
  }