Problems Facing Consultant Engineers and Integrated Solutions for Improved Project Performance in the Nigerian Construction Industry: A Survey of Professionals in Ibadan

Taiwo Zainab Busari Sunday Olufemi Adesogan

Subject area: Science,Engineering and Technology  ·  Area of research: Integrated Solutions

Abstract

Consultant engineers are central to the delivery of construction projects, yet project failures in Nigeria are frequently linked to deficiencies in design, supervision and professional conduct. Existing studies have largely examined these deficiencies in isolation. This study assessed fifteen consultant-related problems in terms of frequency and severity, examined their perceived effect on project cost, time, quality and safety, and evaluated fifteen technological, managerial and regulatory solutions among professionals who work with consultant engineers in Ibadan, Nigeria. A descriptive cross-sectional survey was conducted using a structured questionnaire (Cronbach’s alpha = 0.86 in the pilot study) administered to 60 professionals with at least five years of field experience, comprising consultant engineers (n = 22), contractor site engineers (n = 17), client project managers (n = 17) and other professionals (n = 4). Data were analysed using descriptive statistics, the Relative Importance Index (RII), a one-sample t-test and Friedman tests. Respondents rated the problems as low in frequency (overall mean = 2.22 out of 5) but high in severity (overall mean = 4.08). Inadequate geotechnical investigation was the most frequently reported problem (mean = 2.42), whereas lack of specialised building services expertise was the most severe (mean = 4.23). Respondents agreed strongly that these problems affect project performance (mean agreement = 4.27), and all fifteen solutions were strongly endorsed; however, the ranking items did not produce a valid priority order, and no significant differences were found within solution groups (Friedman test, p > 0.05). The findings indicate that consultant-related problems, although perceived as infrequent, carry serious consequences for project performance, and that technological, managerial and regulatory measures are supported as complementary remedies. The conclusions are limited by a small purposive sample drawn from one city and by the reliance on perception-based data.

Keywords

Consultant engineers, Construction project performance, Geotechnical investigation, Integrated solutions, Nigeria, Relative Importance Index

References

[1] Adegbenro G (2025, November 12). Engineers, not govt, behind Nigeria’s bad roads – Adegbenro blows hot. Roving Reporters. https://www.rovingreportersngr.com/2025/11/12/engineers-not-govt-behind-nigerias-bad-roads-adegbenro-blows-hot/

[2] Adeyemo AA, Amade B (2016). Corruption and construction projects in Nigeria: Manifestations and solutions. PM World Journal, 5(10), 1–14. https://pmworldlibrary.net/wp-content/uploads/2016/10/pmwj51-Oct2016-Adeyemo-Amade-corruption-and-construction-projects-in-nigeria-featured-paper.pdf

[3] Aliu J, Oke AE, Ehiosun LU (2025). Distributed ledger technology integration in Nigerian construction industry: Key drivers. International Journal of Building Pathology and Adaptation, 43(7), 1706–1724. doi:10.1108/IJBPA-02-2024-0044

[4] Aluko OR, Idoro GI, Mewomo MC (2021). Relationship between perceived service quality and client satisfaction indicators of engineering consultancy services in building projects. Journal of Engineering, Design and Technology, 19(2), 557–577. doi:10.1108/JEDT-04-2020-0125

[5] Creswell JW, Creswell JD (2018). Research design: Qualitative, quantitative, and mixed methods approaches (5th ed.). SAGE Publications.

[6] Dosumu OS, Aigbavboa CO (2019). Assessing clients’ satisfaction with the service quality of construction consultants in Lagos, Nigeria. African Journal of Science, Technology, Innovation and Development, 11(6), 771–779. doi:10.1080/20421338.2019.1585676

[7] Ebekozien A, Aigbavboa CO, Aigbedion M, Ogbaini IF, Aginah IL (2023). Integrated project delivery in the Nigerian construction sector: An unexplored approach from the stakeholders’ perspective. Engineering, Construction and Architectural Management, 30(4), 1519–1535. doi:10.1108/ECAM-12-2021-1091

[8] Eisenhardt KM (1989). Agency theory: An assessment and review. Academy of Management Review, 14(1), 57–74. doi:10.5465/amr.1989.4278998

[9] Ejohwomu OA, Oshodi OS, Onifade MK (2016). Causes of conflicts in construction projects in Nigeria: Consultant’s and contractor’s perspective. Nigerian Journal of Technology, 35(2), 270–277. doi:10.4314/njt.v35i2.6

[10] Etikan I, Musa SA, Alkassim RS (2016). Comparison of convenience sampling and purposive sampling. American Journal of Theoretical and Applied Statistics, 5(1), 1–4. doi:10.11648/j.ajtas.20160501.11

[11] Eze EC, Idiake JE (2018). Impact of rework on building project and organisation performance: A view of construction professionals in Nigeria. International Journal of Sustainable Construction Engineering and Technology, 9(1), 29–43. https://publisher.uthm.edu.my/ojs/index.php/IJSCET/article/view/1773

[12] Fagbenro RK, Oyediran OS, Onososen AO (2022). Consulting business workflow and design performance metrics for BIM based construction design in Nigeria. ECS Transactions, 107(1), 1029–1041. doi:10.1149/10701.1029ecst

[13] Field A (2018). Discovering statistics using IBM SPSS statistics (5th ed.). SAGE Publications.

[14] George D, Mallery P (2019). Using SPSS for Windows and Macintosh: Analyzing and understanding data (8th ed.). Pearson.

[15] ICPC (2025, August 14). ICPC, COREN join forces to end shoddy projects and building collapses in Nigeria. Independent Corrupt Practices and Other Related Offences Commission. https://icpc.gov.ng/icpc-coren-sign-mou-to-promote-integrity-ethical-standards-in-the-engineering-profession-regulatory-system/

[16] Ikediashi DI, Ogwueleka AC (2016). Assessing the use of ICT systems and their impact on construction project performance in the Nigerian construction industry. Journal of Engineering, Design and Technology, 14(2), 252–276. doi:10.1108/JEDT-08-2014-0047

[17] Iroha EV, Watanabe T, Tsuchiya S (2024). Flawed institutional structures: Project managers underutilized in Nigeria’s construction industry. Buildings, 14(3), Article 807. doi:10.3390/buildings14030807

[18] Jega AN, Rango GT, Fakai MB, Olawumi BA, Shagari AI (2025). Assessing the effects of contract variations on building construction delivery. African Journal of Environmental Sciences and Renewable Energy, 21(1), 94–112. doi:10.62154/ajesre.2025.021.01015

[19] Jensen MC, Meckling WH (1976). Theory of the firm: Managerial behavior, agency costs and ownership structure. Journal of Financial Economics, 3(4), 305–360. doi:10.1016/0304-405X(76)90026-X

[20] Odeyemi SO, Akinpelu MA, Atoyebi OD (2019). Geotechnical investigation deficiencies and building foundation failures in Nigeria. Nigerian Journal of Technology, 38(3), 789–800.

[21] Oke AE, Kineber AF, Albukhari I, Othman I, Kingsley C (2021). Assessment of cloud computing success factors for sustainable construction industry: The case of Nigeria. Buildings, 11(2), Article 36. doi:10.3390/buildings11020036

[22] Oyeyipo O, Adeyemi B, Osuizugbo IC, Ojelabi RA (2025). Service quality of building services consultants in building project delivery: Clients’ perspectives. International Journal of Construction Management. Advance online publication.

[23] Project Management Institute (2021). A Guide to the Project Management Body of Knowledge (PMBOK Guide) (7th ed.). Newtown Square, PA: Project Management Institute.

[24] Saunders MNK, Lewis P, Thornhill A (2019). Research methods for business students (8th ed.). Pearson Education.

[25] Tanko BL, Abdullah F, Ramly ZM (2017). Stakeholders assessment of constraints to project delivery in the Nigerian construction industry. International Journal of Built Environment and Sustainability, 4(1), 56–62. doi:10.11113/ijbes.v4.n1.160

[26] Unegbu HCO, Yawas DS, Dan-Asabe B (2022). An investigation of the relationship between project performance measures and project management practices of construction projects for the construction industry in Nigeria. Journal of King Saud University – Engineering Sciences, 34(4), 240–249. doi:10.1016/j.jksues.2020.09.008

[27] Unegbu HCO, Yawas DS, Dan-Asabe B, Alabi AA (2025). Measures for overcoming sustainable construction barriers in the Nigerian construction industry. Discover Civil Engineering, 2(1), Article 14. doi:10.1007/s44290-025-00189-w

How to cite this paper

Taiwo Zainab Busari, Sunday Olufemi Adesogan "Problems Facing Consultant Engineers and Integrated Solutions for Improved Project Performance in the Nigerian Construction Industry: A Survey of Professionals in Ibadan" Iconic Research And Engineering Journals Volume 10 Issue 5 2026 Page 3257-3270
Taiwo Zainab Busari, Sunday Olufemi Adesogan "Problems Facing Consultant Engineers and Integrated Solutions for Improved Project Performance in the Nigerian Construction Industry: A Survey of Professionals in Ibadan" Iconic Research And Engineering Journals, vol. 10, no. 5, Nov. 2026
Taiwo Zainab Busari, Sunday Olufemi Adesogan (2026). Problems Facing Consultant Engineers and Integrated Solutions for Improved Project Performance in the Nigerian Construction Industry: A Survey of Professionals in Ibadan. Iconic Research And Engineering Journals, 10(5).
Taiwo Zainab Busari, Sunday Olufemi Adesogan "Problems Facing Consultant Engineers and Integrated Solutions for Improved Project Performance in the Nigerian Construction Industry: A Survey of Professionals in Ibadan" Iconic Research And Engineering Journals, vol. 10, no. 5, Nov. 2026.
@article{1725194,
      author = {Taiwo Zainab Busari, Sunday Olufemi Adesogan},
      title = {Problems Facing Consultant Engineers and Integrated Solutions for Improved Project Performance in the Nigerian Construction Industry: A Survey of Professionals in Ibadan},
      journal = {Iconic Research And Engineering Journals},
      year = {2026},
      volume = {10},
      number = {5},
      pages = {3257-3270},
      issn = {2456-8880},
      url = {https://www.irejournals.com/formatedpaper/1725194.pdf},
      abstract = {Consultant engineers are central to the delivery of construction projects, yet project failures in Nigeria are frequently linked to deficiencies in design, supervision and professional conduct. Existing studies have largely examined these deficiencies in isolation. This study assessed fifteen consultant-related problems in terms of frequency and severity, examined their perceived effect on project cost, time, quality and safety, and evaluated fifteen technological, managerial and regulatory solutions among professionals who work with consultant engineers in Ibadan, Nigeria. A descriptive cross-sectional survey was conducted using a structured questionnaire (Cronbach’s alpha = 0.86 in the pilot study) administered to 60 professionals with at least five years of field experience, comprising consultant engineers (n = 22), contractor site engineers (n = 17), client project managers (n = 17) and other professionals (n = 4). Data were analysed using descriptive statistics, the Relative Importance Index (RII), a one-sample t-test and Friedman tests. Respondents rated the problems as low in frequency (overall mean = 2.22 out of 5) but high in severity (overall mean = 4.08). Inadequate geotechnical investigation was the most frequently reported problem (mean = 2.42), whereas lack of specialised building services expertise was the most severe (mean = 4.23). Respondents agreed strongly that these problems affect project performance (mean agreement = 4.27), and all fifteen solutions were strongly endorsed; however, the ranking items did not produce a valid priority order, and no significant differences were found within solution groups (Friedman test, p > 0.05). The findings indicate that consultant-related problems, although perceived as infrequent, carry serious consequences for project performance, and that technological, managerial and regulatory measures are supported as complementary remedies. The conclusions are limited by a small purposive sample drawn from one city and by the reliance on perception-based data.},
      keywords = {Consultant engineers, Construction project performance, Geotechnical investigation, Integrated solutions, Nigeria, Relative Importance Index},
      month = {November},
  }