Critical Path Method Adoption, Delay Factors and Schedule Crashing in Lagos Construction Projects: A Survey and a Proposed Six-Stage Framework
Subject area: Science,Engineering and Technology · Area of research: Construction Engineering and Management
Abstract
Background: Construction projects in Lagos State often finish late, although the Critical Path Method (CPM) is well established. Earlier Lagos studies ranked causes of delay but did not measure CPM adoption, delay on critical activities and the judged effectiveness of crashing in one sample. Methods: A cross-sectional questionnaire survey was carried out among engineers, builders, project managers and architects working in four Lagos local government areas. Of 250 questionnaires distributed, 99 were returned (39.6%), and 83 to 96 responses were valid for each analysis. Data were analysed with descriptive statistics, the Relative Importance Index, one-sample t-tests, Pearson correlation and one-way ANOVA. Results: CPM adoption (M = 3.72, SD = 0.90) and perceived crashing effectiveness (M = 3.61, SD = 0.77) were above the scale midpoint, with large effects (d ≈ 0.80). Among 16 delay factors, labour shortages and low productivity (M = 3.64), bad weather, design changes, equipment constraints and governance issues ranked highest. Agreement that compression follows cost-benefit analysis was only moderate (M = 3.41), and perceived crashing effectiveness was unrelated to adoption (r = .15, p = .156). Early contractor involvement (M = 4.09) was the most supported strategy. Conclusion: Lagos professionals report wide use of CPM, but training and cost-based recovery decisions are weak points. A six-stage framework is proposed for validation. The findings rest on perceptions from a non-probability sample and do not show that CPM reduces delay.
Keywords
construction delay, critical path method, Lagos State, project scheduling, schedule crashing
References
[1] Sanni-Anibire MO, Mohamad Zin R, Olatunji SO. Causes of delay in the global construction industry: a meta analytical review. Int J Constr Manage. 2022;22(8):1395–1407. https://doi.org/10.1080/15623599.2020.1716132
[2] Durdyev S, Hosseini MR. Causes of delays on construction projects: a comprehensive list. Int J Manag Projects Bus. 2020;13(1):20–46. https://doi.org/10.1108/IJMPB-09-2018-0178
[3] Zidane YJT, Andersen B. The top 10 universal delay factors in construction projects. Int J Manag Projects Bus. 2018;11(3):650–672. https://doi.org/10.1108/IJMPB-05-2017-0052
[4] Kadiri DS, Akintoye AA, Onabanjo BO. Comparative assessment of causes of delay in public and private building projects in Lagos State, Nigeria. Uniosun J Eng Environ Sci. 2019;1(2). https://doi.org/10.36108/ujees/9102.10.0240
[5] Joseph OS, Fadugba OG, Oluyemi-Ayibiowu BD, Uduebor MA, Olu-Matins OA. An expert analytical approach to reducing construction project delays from ineffective scheduling. KIU J Sci Eng Technol. 2025;4(1):142–150. https://doi.org/10.59568/KJSET-2025-4-1-14
[6] Lan R, Adenuga O, Awolusi I. Professionals’ perspectives on the factors causing construction project failures in developing countries: a case study of Lagos metropolis. Int J Constr Manage. 2026;26(3). https://doi.org/10.1080/15623599.2025.2528451
[7] Oyediran AO, Akinradewo O, Onososen AO, Koriko O. Key factors contributing to construction delays in high-rise building projects: a case study of Nigeria’s developing urban landscape. J Facilities Manage. 2026;24(1):114–133. https://doi.org/10.1108/JFM-05-2024-0056
[8] Mubarak SA. Construction project scheduling and control. 4th ed. Hoboken, NJ: Wiley; 2019.
[9] Project Management Institute. Practice standard for scheduling. 3rd ed. Newtown Square, PA: Project Management Institute; 2019.
[10] Jamal MS, Abdelaty A, Mehany MSHM, Shrestha KJ, Yamany MS. Assessment of construction baseline schedule quality in transportation projects. Organ Technol Manage Constr. 2026;18(1):33–50. https://doi.org/10.2478/otmcj-2026-0003
[11] Ballesteros-Pérez P, Larsen GD, González-Cruz MC. Do projects really end late? On the shortcomings of the classical scheduling techniques. J Technol Sci Educ. 2018;8(1):17–33.
[12] ElSahly OM, Ahmed S, Abdelfatah A. Systematic review of the time-cost optimization models in construction management. Sustainability. 2023;15(6):5578. https://doi.org/10.3390/su15065578
[13] Ballesteros-Pérez P, Elamrousy KM, González-Cruz MC. Non-linear time-cost trade-off models of activity crashing: application to construction scheduling and project compression with fast-tracking. Autom Constr. 2019;97:229–240. https://doi.org/10.1016/j.autcon.2018.11.001
[14] Creswell JW, Creswell JD. Research design: qualitative, quantitative, and mixed methods approaches. 5th ed. Thousand Oaks, CA: SAGE; 2018.
[15] Campbell S, et al. Purposive sampling: complex or simple? Research case examples. J Res Nurs. 2020;25(8):652–661. https://doi.org/10.1177/1744987120927206
[16] Parker C, Scott S, Geddes A. Snowball sampling. In: SAGE Research Methods Foundations. London: SAGE; 2019. https://doi.org/10.4135/9781526421036831710
[17] Lakens D. Sample size justification. Collabra: Psychol. 2022;8(1):33267. https://doi.org/10.1525/collabra.33267
[18] Robitzsch A. Why ordinal variables can (almost) always be treated as continuous variables: clarifying assumptions of robust continuous and ordinal factor analysis estimation methods. Front Educ. 2020;5:589965. https://doi.org/10.3389/feduc.2020.589965
[19] Taber KS. The use of Cronbach’s alpha when developing and reporting research instruments in science education. Res Sci Educ. 2018;48(6):1273–1296. https://doi.org/10.1007/s11165-016-9602-2
[20] Andersen H, Mayerl J. Responding to socially desirable and undesirable topics: different types of response behaviour? Methods Data Anal. 2019;13(1):7–35. https://doi.org/10.12758/mda.2018.06
[21] Rooshdi RRRM, Abd Majid MZ, Sahamir SR, Ismail NAA. Relative importance index of sustainable design and construction activities criteria for green highway. Chem Eng Trans. 2018;63:151–156. https://doi.org/10.3303/CET1863026
[22] Funder DC, Ozer DJ. Evaluating effect size in psychological research: sense and nonsense. Adv Methods Pract Psychol Sci. 2019;2(2):156–168. https://doi.org/10.1177/2515245919847202
[23] Delacre M, Leys C, Mora YL, Lakens D. Taking parametric assumptions seriously: arguments for the use of Welch’s F-test instead of the classical F-test in one-way ANOVA. Int Rev Soc Psychol. 2019;32(1):13. https://doi.org/10.5334/irsp.198
[24] Sauder DC, DeMars CE. An updated recommendation for multiple comparisons. Adv Methods Pract Psychol Sci. 2019;2(1):26–44. https://doi.org/10.1177/2515245918808784
[25] Federal Republic of Nigeria. Nigeria Data Protection Act, 2023. Official Gazette of the Federal Republic of Nigeria. Abuja: Federal Government of Nigeria; 2023.
[26] Aredah AS, Baraka MA, ElKhafif M. Project scheduling techniques within a building information modeling (BIM) environment: a survey study. IEEE Eng Manag Rev. 2019;47(2):133–143. https://doi.org/10.1109/EMR.2019.2916365
[27] Ugulu RA, Arewa A, Allen S. Project specific constraints influencing productivity of tradespeople in the Nigerian construction industry. Built Environ Project Asset Manage. 2020;10(1):94–109. https://doi.org/10.1108/BEPAM-10-2018-0124
[28] Egwim CN, Alaka H, Toriola-Coker LO, Balogun H, Ajayi S, Oseghale R. Extraction of underlying factors causing construction projects delay in Nigeria. J Eng Des Technol. 2023;21(5):1323–1342. https://doi.org/10.1108/JEDT-04-2021-0211
[29] Shash AA, AbuAlnaja FM. Causes of material delays in capital projects in Saudi Arabia. Int J Constr Manage. 2023;23(7):1109–1117. https://doi.org/10.1080/15623599.2021.1956294
[30] Ismaila U, Jung W, Park CY. Delay causes and types in Nigerian power construction projects. Energies. 2022;15(3):814. https://doi.org/10.3390/en15030814
[31] Negesa AB. Assessing the causes of time overrun in building and road construction projects: the case of Addis Ababa City, Ethiopia. J Eng. 2022;2022:8479064. https://doi.org/10.1155/2022/8479064
[32] Akin FD, Polat G, Turkoglu H, Damci A. A crashing-based time-cost trade-off model considering quality cost and contract clauses. Int J Constr Manage. 2023;23(6):954–963. https://doi.org/10.1080/15623599.2021.1946899
[33] Lee C. Evaluating construction delays using productivity-based resource reallocation for economic feasibility. Eng Constr Archit Manage. 2023;30(4):1679–1696. https://doi.org/10.1108/ECAM-09-2019-0503
[34] Elkabalawy M, Moselhi O. Optimized resource-constrained method for project schedule compression. Eng Constr Archit Manage. 2022;29(5):2106–2129. https://doi.org/10.1108/ECAM-12-2020-1019
[35] Fagiar M, Mohamed Y, AbouRizk S. Simulation-assisted project data integration for development and analysis of as-built schedules. Buildings. 2023;13(4):974. https://doi.org/10.3390/buildings13040974
[36] Vo HM, Yang JB, Rangasamy V. A comprehensive review of delay analysis techniques for solving concurrent delays. Eng Constr Archit Manage. 2025;32(5):3495–3521. https://doi.org/10.1108/ECAM-10-2023-1022
[37] Assafi MN, Hossain MM, Chileshe N, Datta SD. Development and validation of a framework for preventing and mitigating construction delay using 4D BIM platform in Bangladeshi construction sector. Constr Innov. 2023;23(5):1255–1278. https://doi.org/10.1108/CI-08-2021-0160
[38] Sadeghi S, Niu C, Marjani T, Lotfi R. Machine learning-enabled construction project management: systematic review, comparative performance synthesis and implementation framework. Built Environ Project Asset Manage. 2026;16(3):461–483. https://doi.org/10.1108/BEPAM-11-2024-0264
[39] Pan Y, Zhang L. Roles of artificial intelligence in construction engineering and management: a critical review and future trends. Autom Constr. 2021;122:103517. https://doi.org/10.1016/j.autcon.2020.103517
How to cite this paper
@article{1725414,
author = {Y. L. Ogunsola, A. K. Coker},
title = {Critical Path Method Adoption, Delay Factors and Schedule Crashing in Lagos Construction Projects: A Survey and a Proposed Six-Stage Framework},
journal = {Iconic Research And Engineering Journals},
year = {2026},
volume = {10},
number = {5},
pages = {4071-4082},
issn = {2456-8880},
url = {https://www.irejournals.com/formatedpaper/1725414.pdf},
abstract = {Background: Construction projects in Lagos State often finish late, although the Critical Path Method (CPM) is well established. Earlier Lagos studies ranked causes of delay but did not measure CPM adoption, delay on critical activities and the judged effectiveness of crashing in one sample. Methods: A cross-sectional questionnaire survey was carried out among engineers, builders, project managers and architects working in four Lagos local government areas. Of 250 questionnaires distributed, 99 were returned (39.6%), and 83 to 96 responses were valid for each analysis. Data were analysed with descriptive statistics, the Relative Importance Index, one-sample t-tests, Pearson correlation and one-way ANOVA. Results: CPM adoption (M = 3.72, SD = 0.90) and perceived crashing effectiveness (M = 3.61, SD = 0.77) were above the scale midpoint, with large effects (d ≈ 0.80). Among 16 delay factors, labour shortages and low productivity (M = 3.64), bad weather, design changes, equipment constraints and governance issues ranked highest. Agreement that compression follows cost-benefit analysis was only moderate (M = 3.41), and perceived crashing effectiveness was unrelated to adoption (r = .15, p = .156). Early contractor involvement (M = 4.09) was the most supported strategy. Conclusion: Lagos professionals report wide use of CPM, but training and cost-based recovery decisions are weak points. A six-stage framework is proposed for validation. The findings rest on perceptions from a non-probability sample and do not show that CPM reduces delay.},
keywords = {construction delay, critical path method, Lagos State, project scheduling, schedule crashing},
month = {November},
}