Allocating Schedule Contingency in Multi-Site Engineering Rollouts Under Shared Delay Risk

Prince Keshi

Subject area: Science,Engineering and Technology  ·  Area of research: Engineering Project Scheduling and Risk

DOI: 10.64388/ire1725645

Abstract

Multi-site engineering rollouts are reported against one programme date, yet each building is handed back to its users on its own date. This paper asks where a fixed amount of schedule contingency should sit when some delays strike one site and others, such as a supplier setback, strike several sites at once. Public records of the New York City School Construction Authority (SCA) for school security-camera installations show that lateness is strongly shared within contract bundles: the intraclass correlation of design-phase lateness is 0.93, and none of the 15 construction bundles due by December 2022 had finished within 15 days of its planned end. A Monte Carlo model of two real three-school bundles, with crew, delivery and access constraints, compared four placements of the same contingency against identical disruptions. The best placement depends on whether handover dates can still be set. In a high-dependence scenario informed by the SCA records, with 12 days of contingency, a pooled bundle reserve cut expected late handovers from 3.71 of six under equal site buffers to 2.36, but promised dates 5.5 working days later on average. Against six dates already agreed, a tight plan with an end-of-programme reserve protected them best, with 2.82 late handovers against 3.49 for pooled scheduling. Assuming independent supplier delays barely changed mean lateness but hid clustered failure: the first tested contingency keeping four or more late handovers below 10% rose from 18 days to 39 with fully shared delays. A placement guide for managers follows.

Keywords

buffer allocation, correlated risk, handover reliability, Monte Carlo simulation, multi-site programmes, public buildings, schedule contingency

References

[1] Ballard, G. and Howell, G. (1998) Shielding production: essential step in production control. Journal of Construction Engineering and Management, 124(1), 11-17. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:1(11)

[2] Ballou, R.H., Rahardja, H. and Sakai, N. (2002) Selected country circuity factors for road travel distance estimation. Transportation Research Part A: Policy and Practice, 36(9), 843-848. https://doi.org/10.1016/S0965-8564(01)00044-1

[3] Clemen, R.T. and Reilly, T. (1999) Correlations and copulas for decision and risk analysis. Management Science, 45(2), 208-224. https://doi.org/10.1287/mnsc.45.2.208

[4] Department for Energy Security and Net Zero (2023) Greenhouse gas reporting: conversion factors 2023, flat file (updated 28 June 2023). London: DESNZ. https://www.gov.uk/government/publications/greenhouse-gas-reporting-conversion-factors-2023

[5] Goldratt, E.M. (1997) Critical Chain. Great Barrington, MA: North River Press.

[6] Grimm, V., Revilla, E., Berger, U., Jeltsch, F., Mooij, W.M., Railsback, S.F., Thulke, H.H., Weiner, J., Wiegand, T. and DeAngelis, D.L. (2005) Pattern-oriented modeling of agent-based complex systems: lessons from ecology. Science, 310(5750), 987-991. https://doi.org/10.1126/science.1116681

[7] Harris, R.B. and Ioannou, P.G. (1998) Scheduling projects with repeating activities. Journal of Construction Engineering and Management, 124(4), 269-278. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:4(269)

[8] Herroelen, W. and Leus, R. (2004) Robust and reactive project scheduling: a review and classification of procedures. International Journal of Production Research, 42(8), 1599-1620. https://doi.org/10.1080/00207540310001638055

[9] Hopp, W.J. and Spearman, M.L. (2008) Factory Physics. 3rd edn. New York: McGraw-Hill.

[10] Lambrechts, O., Demeulemeester, E. and Herroelen, W. (2008) Proactive and reactive strategies for resource-constrained project scheduling with uncertain resource availabilities. Journal of Scheduling, 11(2), 121-136. https://doi.org/10.1007/s10951-007-0021-0

[11] Law, A.M. (2015) Simulation Modeling and Analysis. 5th edn. New York: McGraw-Hill.

[12] Leach, L.P. (1999) Critical chain project management improves project performance. Project Management Journal, 30(2), 39-51. https://doi.org/10.1177/875697289903000207

[13] McGraw, K.O. and Wong, S.P. (1996) Forming inferences about some intraclass correlation coefficients. Psychological Methods, 1(1), 30-46. https://doi.org/10.1037/1082-989X.1.1.30

[14] New York City School Construction Authority (2022) Capital Project Schedules and Budgets [dataset]. NYC Open Data, version published 8 December 2022. https://data.cityofnewyork.us/Housing-Development/Capital-Project-Schedules-and-Budgets/2xh6-psuq

[15] NYC Department of Education (2020) 2019-2020 School Point Locations [dataset]. NYC Open Data. https://data.cityofnewyork.us/Education/2019-2020-School-Point-Locations/a3nt-yts4

[16] NYC Mayor's Office of Operations (2022) Mayor's Management Report, Fiscal 2022: School Construction Authority. New York: City of New York. https://www.nyc.gov/assets/operations/downloads/pdf/mmr2022/sca.pdf

[17] NYC Mayor's Office of Operations (2023a) Preliminary Mayor's Management Report, Fiscal 2023: School Construction Authority. New York: City of New York. https://www.nyc.gov/assets/operations/downloads/pdf/pmmr2023/sca.pdf

[18] NYC Mayor's Office of Operations (2023b) Preliminary Mayor's Management Report, Fiscal 2023: School Construction Authority indicator definitions. New York: City of New York. https://www.nyc.gov/assets/operations/downloads/pdf/pmmr2023/sca_idf.pdf

[19] Ökmen, Ö. and Öztaş, A. (2008) Construction project network evaluation with correlated schedule risk analysis model. Journal of Construction Engineering and Management, 134(1), 49-63. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:1(49)

[20] Schatteman, D., Herroelen, W., Van de Vonder, S. and Boone, A. (2008) Methodology for integrated risk management and proactive scheduling of construction projects. Journal of Construction Engineering and Management, 134(11), 885-893. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:11(885)

[21] Trietsch, D., Mazmanyan, L., Gevorgyan, L. and Baker, K.R. (2012) Modeling activity times by the Parkinson distribution with a lognormal core: theory and validation. European Journal of Operational Research, 216(2), 386-396. https://doi.org/10.1016/j.ejor.2011.07.054

[22] Tukel, O.I., Rom, W.O. and Eksioglu, S.D. (2006) An investigation of buffer sizing techniques in critical chain scheduling. European Journal of Operational Research, 172(2), 401-416. https://doi.org/10.1016/j.ejor.2004.10.019

[23] Van de Vonder, S., Demeulemeester, E., Herroelen, W. and Leus, R. (2005) The use of buffers in project management: the trade-off between stability and makespan. International Journal of Production Economics, 97(2), 227-240. https://doi.org/10.1016/j.ijpe.2004.08.004

How to cite this paper

Prince Keshi "Allocating Schedule Contingency in Multi-Site Engineering Rollouts Under Shared Delay Risk" Iconic Research And Engineering Journals Volume 7 Issue 2 2023 Page 891-910 https://doi.org/10.64388/ire1725645
Prince Keshi "Allocating Schedule Contingency in Multi-Site Engineering Rollouts Under Shared Delay Risk" Iconic Research And Engineering Journals, vol. 7, no. 2, Aug. 2023, doi: https://doi.org/10.64388/ire1725645
Prince Keshi (2023). Allocating Schedule Contingency in Multi-Site Engineering Rollouts Under Shared Delay Risk. Iconic Research And Engineering Journals, 7(2). doi: https://doi.org/10.64388/ire1725645
Prince Keshi "Allocating Schedule Contingency in Multi-Site Engineering Rollouts Under Shared Delay Risk" Iconic Research And Engineering Journals, vol. 7, no. 2, Aug. 2023. Crossref, https://doi.org/10.64388/ire1725645
@article{1725645,
      author = {Prince Keshi},
      title = {Allocating Schedule Contingency in Multi-Site Engineering Rollouts Under Shared Delay Risk},
      journal = {Iconic Research And Engineering Journals},
      year = {2023},
      volume = {7},
      number = {2},
      pages = {891-910},
      issn = {2456-8880},
      url = {https://www.irejournals.com/formatedpaper/1725645.pdf},
      abstract = {Multi-site engineering rollouts are reported against one programme date, yet each building is handed back to its users on its own date. This paper asks where a fixed amount of schedule contingency should sit when some delays strike one site and others, such as a supplier setback, strike several sites at once. Public records of the New York City School Construction Authority (SCA) for school security-camera installations show that lateness is strongly shared within contract bundles: the intraclass correlation of design-phase lateness is 0.93, and none of the 15 construction bundles due by December 2022 had finished within 15 days of its planned end. A Monte Carlo model of two real three-school bundles, with crew, delivery and access constraints, compared four placements of the same contingency against identical disruptions. The best placement depends on whether handover dates can still be set. In a high-dependence scenario informed by the SCA records, with 12 days of contingency, a pooled bundle reserve cut expected late handovers from 3.71 of six under equal site buffers to 2.36, but promised dates 5.5 working days later on average. Against six dates already agreed, a tight plan with an end-of-programme reserve protected them best, with 2.82 late handovers against 3.49 for pooled scheduling. Assuming independent supplier delays barely changed mean lateness but hid clustered failure: the first tested contingency keeping four or more late handovers below 10% rose from 18 days to 39 with fully shared delays. A placement guide for managers follows.},
      keywords = {buffer allocation, correlated risk, handover reliability, Monte Carlo simulation, multi-site programmes, public buildings, schedule contingency},
      month = {August},
      doi = {https://doi.org/10.64388/ire1725645}
  }