Schedule Risk Analysis and Recovery Planning for Large-Scale Entertainment Projects in Saudi Arabia
Subject area: Management and Commerce · Area of research: Project Scheduling and Risk Management
DOI: 10.64388/ire1725647
Abstract
Large entertainment developments combine conventional building works with specialist equipment, controls integration, commissioning and operator mobilisation. A schedule can show physical progress while the activities required for a safe opening fall behind. This paper develops a schedule risk and recovery framework for Saudi entertainment projects through a structured narrative synthesis of Saudi construction delay research, project scheduling literature and professional guidance. It links the contractual baseline to a logic driven current forecast, then connects risk drivers and opening dependencies to specific recovery decisions. An illustrative network compares a delayed forecast with procurement acceleration, site resequencing and coordinated recovery. The example shows how a supplier intervention can move the critical path to utility readiness and how a larger recovery package can improve the likelihood of a target while leaving substantial residual exposure. The proposed approach preserves commissioning and acceptance requirements, assigns accountability for cross package handovers and retains auditable programme versions. Its contribution is a decision sequence that connects construction progress, milestone risk and operational readiness in the same planning process.
Keywords
Schedule risk analysis, recovery planning, entertainment construction, Saudi Vision 2030, critical path, commissioning
References
[1] AACE International (2017). Forensic schedule analysis (Recommended Practice 29R-03) [Internet]. 2017. Available from: https://web.aacei.org/docs/default-source/toc/toc_29r-03.pdf
[2] AACE International (2017). Prospective time impact analysis as applied in construction (Recommended Practice 52R-06) [Internet]. 2017. Available from: https://web.aacei.org/docs/default-source/toc/toc_52r-06.pdf
[3] AACE International (2019). Integrated cost and schedule risk analysis using risk drivers and Monte Carlo simulation of a CPM model (Recommended Practice 57R-09) [Internet]. 2019. Available from: https://web.aacei.org/docs/default-source/toc/toc_57r-09.pdf
[4] Al-Kharashi A, Skitmore M (2009). Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics, 27(1), 3–23. https://doi.org/10.1080/01446190802541457
[5] Alajmi AM, Memon ZA (2022). A review on significant factors causing delays in Saudi Arabia construction projects. Smart Cities, 5(4), 1465–1487. https://doi.org/10.3390/smartcities5040075
[6] AlSehaimi A, Koskela L, Tzortzopoulos P (2013). Need for alternative research approaches in construction management: Case of delay studies. Journal of Management in Engineering, 29(4), 407–413. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000148
[7] ASHRAE (n.d.). Principles of building commissioning: ASHRAE Guideline 0 and Standard 202 [Internet]. Available from: https://www.ashrae.org/professional-development/all-instructor-led-training/catalog-of-instructor-led-training/principles-of-building-commissioning-ashrae-guideline-0-and-standard-202
[8] Assaf SA, Al-Hejji S (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. https://www.sciencedirect.com/science/article/pii/S0263786305001262
[9] Assaf SA, Al-Khalil M, Al-Hazmi M (1995). Causes of delay in large building construction projects. Journal of Management in Engineering, 11(2), 45–50. https://doi.org/10.1061/(ASCE)0742-597X(1995)11:2(45)
[10] Ballard HG (2000). The last planner system of production control [Doctoral dissertation, University of Birmingham] [Internet]. 2000. Available from: https://leanconstruction.org/wp-content/uploads/2022/09/the-last-planner-system-of-production-control-ballard2000-dissertation.pdf
[11] De P, Dunne EJ, Ghosh JB, Wells CE (1995). The discrete time-cost tradeoff problem revisited. European Journal of Operational Research, 81(2), 225–238. https://www.sciencedirect.com/science/article/abs/pii/037722179400187H
[12] Government Accountability Office (2015). Schedule assessment guide: Best practices for project schedules (GAO-16-89G) [Internet]. 2015. Available from: https://www.gao.gov/products/gao-16-89g
[13] Herroelen W, Leus R (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289–306. https://www.sciencedirect.com/science/article/pii/S0377221704002401
[14] Hulett DT (2009). Practical schedule risk analysis [Internet]. Gower; 2009. Available from: https://www.routledge.com/Practical-Schedule-Risk-Analysis/Hulett/p/book/9781032837963
[15] Kelley JE, Walker MR (1959). Critical-path planning and scheduling. Proceedings of the Eastern Joint IRE-AIEE-ACM Computer Conference, 160–173. https://doi.org/10.1145/1460299.1460318
[16] Malcolm DG, Roseboom JH, Clark CE, Fazar W (1959). Application of a technique for research and development program evaluation. Operations Research, 7(5), 646–669. https://doi.org/10.1287/opre.7.5.646
[17] NASA (n.d.). Schedule management overview [Internet]. Available from: https://www.nasa.gov/ocfo/ppc-corner/schedule-management-overview/
[18] Public Investment Fund (2023). SEVEN breaks ground at SAR 1.3 billion entertainment destination in Almadinah [Internet]. 2023. Available from: https://www.pif.gov.sa/en/news-and-insights/newswire/2023/seven-breaks-ground-at-sar-13-billion-entertainment-destination-in-almadinah/
[19] Quality of Life Program (2025). Quality of Life Program annual report 2024 [Internet]. 2025. Available from: https://www.vision2030.gov.sa/media/2klnw2y0/qol_annual_report_2024_en.pdf
[20] Ramanathan C, Narayanan SP, Idrus AB (2012). Construction delays causing risks on time and cost: A critical review. Construction Economics and Building, 12(1). https://doi.org/10.5130/AJCEB.v12i1.2330
[21] Saudi Vision 2030 (2025). Saudi Vision 2030 annual report 2024 [Internet]. 2025. Available from: https://www.vision2030.gov.sa/media/r3ij40wu/en-annual-report-vision2030-2024.pdf
[22] Society of Construction Law (2017). Delay and disruption protocol (2nd ed.) [Internet]. 2017. Available from: https://www.scl.org.uk/resources/delay-disruption-protocol
[23] Van de Vonder S, Demeulemeester E, Herroelen W, Leus R (2005). The use of buffers in project management: The trade-off between stability and makespan. International Journal of Production Economics, 97(2), 227–240. https://www.sciencedirect.com/science/article/pii/S0925527304003020
[24] Vanhoucke M, Vandevoorde S (2007). A simulation and evaluation of earned value metrics to forecast the project duration. Journal of the Operational Research Society, 58(10), 1361–1374. https://doi.org/10.1057/palgrave.jors.2602296
[25] Zhasmukhambetova A, Evdorides H, Davies RJ (2025). Integrating risk assessment and scheduling in highway construction: A systematic review of techniques, challenges, and hybrid methodologies. Future Transportation, 5(3), 85. https://doi.org/10.3390/futuretransp5030085
How to cite this paper
@article{1725647,
author = {Pavithran Ravikumar},
title = {Schedule Risk Analysis and Recovery Planning for Large-Scale Entertainment Projects in Saudi Arabia},
journal = {Iconic Research And Engineering Journals},
year = {2026},
volume = {10},
number = {5},
pages = {5521-5531},
issn = {2456-8880},
url = {https://www.irejournals.com/formatedpaper/1725647.pdf},
abstract = {Large entertainment developments combine conventional building works with specialist equipment, controls integration, commissioning and operator mobilisation. A schedule can show physical progress while the activities required for a safe opening fall behind. This paper develops a schedule risk and recovery framework for Saudi entertainment projects through a structured narrative synthesis of Saudi construction delay research, project scheduling literature and professional guidance. It links the contractual baseline to a logic driven current forecast, then connects risk drivers and opening dependencies to specific recovery decisions. An illustrative network compares a delayed forecast with procurement acceleration, site resequencing and coordinated recovery. The example shows how a supplier intervention can move the critical path to utility readiness and how a larger recovery package can improve the likelihood of a target while leaving substantial residual exposure. The proposed approach preserves commissioning and acceptance requirements, assigns accountability for cross package handovers and retains auditable programme versions. Its contribution is a decision sequence that connects construction progress, milestone risk and operational readiness in the same planning process.},
keywords = {Schedule risk analysis, recovery planning, entertainment construction, Saudi Vision 2030, critical path, commissioning},
month = {November},
doi = {https://doi.org/10.64388/ire1725647}
}