Home / Current Issue / Paper 1725698
When a Temporary Bypass Becomes the Bottleneck: Machine Learning and Discrete-Event Simulation for Scheduling Water Main Rehabilitation
Subject area: Science,Engineering and Technology · Area of research: Machine Learning
Abstract
Rehabilitating small water mains by cement mortar lining or cured-in-place pipe usually keeps customers supplied through a temporary bypass. Bypass kits are scarce and must be cleaned and moved between streets, so releasing a kit at one site becomes a predecessor of work at another. A quantile regression forest was trained on a synthetic 10-year history of 480 sites calibrated to published utility documents. On a chronological hold-out of 144 sites it reduced mean pinball loss by 9% against historical distributions by work type, and its 90th percentile covered 87.5% of outcomes, against 21.5% for planned durations. In a discrete-event simulation of 1,000 ten-site programmes, better forecasts raised the probability that every kit was released on time from 0.293 to 0.329, and resequencing that protected every waiting site raised it to 0.344; protecting only the next site lowered it to 0.225. A lower booking confidence added 7 to 11 percentage points, and one extra kit added 15 to 17. Customer-hours of interruption varied by under 2% across policies. Results are scenario findings, not utility estimates.
Keywords
water main rehabilitation, temporary bypass, multi-project scheduling, quantile regression forest, discrete-event simulation, shared resources, backfilling
References
[1] City of Cambridge (2026). Inman Street reconstruction project. Department of Public Works, Cambridge, MA. https://www.cambridgema.gov
[2] City of East Providence (2026). 2026 cleaning & lining work. Water Utilities Division, East Providence, RI. https://eastprovidenceri.gov/node/8255
[3] City of Kalamazoo (2026a). Bid 91244-052.0: Specifications and plans, 2026 water main pipe lining project. Kalamazoo, MI. https://www.kalamazoocity.org/files/assets/public/v/1/purchasing/bid-documents/2026/91244-052.0/91244-052.0-specifications_plans.pdf
[4] City of Kalamazoo (2026b). 2026 water main pipe lining project. Kalamazoo, MI. https://www.kalamazoocity.org/Community/Projects/2026/2026-Water-Main-Pipe-Lining-Project
[5] City of Madison (2025). Water pipeline rehabilitation project. Madison Water Utility, Madison, WI. https://www.cityofmadison.com/water/projects/water-pipeline-rehabilitation-project
[6] City of Madison (2026). Water pipeline rehabilitation project - East. Madison Water Utility, Madison, WI. https://www.cityofmadison.com/water/projects/water-pipeline-rehabilitation-project
[7] City of Madison (n.d.-a). Contract 9633: Base bid plans. Department of Public Works, Madison, WI. https://www.cityofmadison.com/water/projects/water-pipeline-rehabilitation-project
[8] City of Madison (n.d.-b). Contract 9788: Signed contract and specifications. Department of Public Works, Madison, WI. https://www.cityofmadison.com/water/projects/water-pipeline-rehabilitation-project
[9] City of Melrose (2025). Notice of work start and bypass hookup. Melrose, MA. https://www.cityofmelrose.org/DocumentCenter/View/2126/2025-07-17_Notice-of-Work-Start-and-Bypass-Hookup_Circuit
[10] City of Somerville (2023). Temporary water main bypass installation, March 23: Oxford, Hershey, Gibbens, School. Somerville, MA. https://voice.somervillema.gov/springhillsewer/news_feed/temporary-water-main-bypass-installation-march-23-oxford-hershey-gibbens-school
[11] Core Aqua (n.d.). Solutions. https://www.coreaqua.com/solutions
[12] Gneiting T, Raftery AE (2007). Strictly proper scoring rules, prediction, and estimation. Journal of the American Statistical Association, 102(477), 359–378.
[13] Gómez Sánchez M, Lalla-Ruiz E, Fernández Gil A, Castro C, Voß S (2023). Resource-constrained multi-project scheduling problem: A survey. European Journal of Operational Research, 309(3), 958–976. https://doi.org/10.1016/j.ejor.2022.09.033
[14] Herroelen W, Leus R (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289–306.
[15] Krüger D, Scholl A (2009). A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times. European Journal of Operational Research, 197(2), 492–508. https://doi.org/10.1016/j.ejor.2008.07.036
[16] Meinshausen N (2006). Quantile regression forests. Journal of Machine Learning Research, 7, 983–999.
[17] Mu'alem AW, Feitelson DG (2001). Utilization, predictability, workloads, and user runtime estimates in scheduling the IBM SP2 with backfilling. IEEE Transactions on Parallel and Distributed Systems, 12(6), 529–543. https://doi.org/10.1109/71.932708
[18] Ofwat (2025). Water supply interruptions: Performance commitment definition. Ofwat, Birmingham, UK. https://www.ofwat.gov.uk/wp-content/uploads/2025/03/Water-supply-interruptions-%E2%80%93-PC-definition.pdf
[19] Park K, Kim M, Bae H (2024). A predictive discrete event simulation for predicting operation times in container terminal. IEEE Access, 12, 58801–58822. https://doi.org/10.1109/ACCESS.2024.3389961
[20] Providence Water (2024). Replacement and rehabilitation of water mains and appurtenances within Edgewood, Cranston, Contract 3-24. Providence, RI. https://www.providenceri.gov/wp-content/uploads/2024/03/PVD24-25-Water-Supply-RFP-Replacement-Rehab-of-Water-Mains-Appurtenances-within-Edgewood-Cranston-Contract-3-24-1.5-Year-Contract-MT44043.pdf
[21] Providence Water (2025). Replacement and rehabilitation of water mains and appurtenances within Lower South Providence, North Section, Contract 2-25. Providence, RI. https://www.providenceri.gov/wp-content/uploads/2024/03/PVD24-25-Water-Supply-RFP-Replacement-Rehab-of-Water-Mains-Appurtenances-within-Edgewood-Cranston-Contract-3-24-1.5-Year-Contract-MT44043.pdf
[22] Tsafrir D, Etsion Y, Feitelson DG (2007). Backfilling using system-generated predictions rather than user runtime estimates. IEEE Transactions on Parallel and Distributed Systems, 18(6), 789–803. https://doi.org/10.1109/TPDS.2007.70606
[23] Unitywater (2026). Pr10179 specification for water supply temporary bypass, Rev. 15. Unitywater, Maroochydore, QLD, Australia. https://www.unitywater.com/building-and-developing/-/media/unitywater/pdf-infrastructure-standards/pr10179---specification-for-water-supply-temporary-bypass.pdf
[24] US EPA (n.d.). EPANET: Application for modeling drinking water distribution systems. US Environmental Protection Agency, Washington, DC. https://www.epa.gov/water-research/epanet
[25] Van Eynde R, Vanhoucke M (2020). Resource-constrained multi-project scheduling: Benchmark datasets and decoupled scheduling. Journal of Scheduling, 23(3), 301–325. https://doi.org/10.1007/s10951-020-00651-w
How to cite this paper
@article{1725698,
author = {Prince Keshi},
title = {When a Temporary Bypass Becomes the Bottleneck: Machine Learning and Discrete-Event Simulation for Scheduling Water Main Rehabilitation},
journal = {Iconic Research And Engineering Journals},
year = {2026},
volume = {10},
number = {5},
pages = {5932-5946},
issn = {2456-8880},
url = {https://www.irejournals.com/formatedpaper/1725698.pdf},
abstract = {Rehabilitating small water mains by cement mortar lining or cured-in-place pipe usually keeps customers supplied through a temporary bypass. Bypass kits are scarce and must be cleaned and moved between streets, so releasing a kit at one site becomes a predecessor of work at another. A quantile regression forest was trained on a synthetic 10-year history of 480 sites calibrated to published utility documents. On a chronological hold-out of 144 sites it reduced mean pinball loss by 9% against historical distributions by work type, and its 90th percentile covered 87.5% of outcomes, against 21.5% for planned durations. In a discrete-event simulation of 1,000 ten-site programmes, better forecasts raised the probability that every kit was released on time from 0.293 to 0.329, and resequencing that protected every waiting site raised it to 0.344; protecting only the next site lowered it to 0.225. A lower booking confidence added 7 to 11 percentage points, and one extra kit added 15 to 17. Customer-hours of interruption varied by under 2% across policies. Results are scenario findings, not utility estimates.},
keywords = {water main rehabilitation, temporary bypass, multi-project scheduling, quantile regression forest, discrete-event simulation, shared resources, backfilling},
month = {November},
}